Separate the Development Site Servicing Plan from the Development Permit

Cut Red Tape
 
 

Issue

When the Development Site Servicing Plan (DSSP) is a condition of Development Permit release it can delay the approval of the Development Permit until the DSSP is approved.

Status: Not feasible

Explanation

There are occasions when the DSSP requirement has been added as an advisory condition which then does not hold up the Development Permit release.

The current DSSP process was reviewed in 2014 and this review will form part of the online eDSSP project proposed for the 2015-2016 work plan. This project is deemed not feasible as it will extend past the Cut Red Tape program end of June 2015.