Share this page Print

Consulting Engineer’s Field Services guidelines

Consulting Engineer’s Field Services Guidelines - 6th edition

Individual forms from Consulting Engineer’s Field Services Guidelines
Number Form name Page
7.1 Water Resources Subdivision Inspection Zone Map 35
7.2 Water Resources, Infrastructure Planning, Development Approvals Zone Map 36
7.3 Roads Subdivision Officer Responsibility Areas 37
7.4 Development Field Order 38
7.5 Construction Completion Certificate 39
7.6 Final Acceptance Certificate 40
7.7 Construction Commencement Notification - Water Resources 41
7.8 Construction Commencement Notification - Roads 42
7.9 Certificate Inspection Request and Appointment Confirmation 43
7.10 Construction Completion Checklist Sheet - Sanitary/Storm Sewers 44
7.11 Construction Completion Checklist Sheet - Water Mains and Hydrants 45
7.12 Construction Completion Checklist Sheet - Sewer and Water Service Connections 46
7.13 Construction Completion Checklist Sheet - Surface Drainage Facilities 47
7.14 Dry Ponds Inspection Checklist Sheet - CCC and FAC Stage - Checklist #11 48
7.15 Wet Ponds / Wetlands Inspection Checklist Sheet at CCC and FAC Stage - Checklist #12 53
7.16 Development Approvals Pond CCC Signoff  - Checklist #7 58
7.17 Construction Completion Inspection Approval Sheet - Underground Utilities 62
7.18 Construction Completion Inspection Approval Sheet - Stormwater Facilities - Development Approvals 63
7.19 Construction Completion Inspection Approval Sheet - Stormwater Facilities - Inspection Services 64
7.20 Construction Completion Certificate Submission Checklist - Underground Utilities 65
7.21 Construction Completion Certificate Submission Checklist - Stormwater Facilities 66
7.22 Electronic Service Card Customer Notice 67
7.23 Final Acceptance Inspection Approval Sheet - Underground Utilities 68
7.24 Final Acceptance Inspection Approval Sheet - Stormwater Facilities - Development Approvals 69
7.25 Final Acceptance Inspection Approval Sheet - Stormwater Facilities - Inspection Services 70
7.26 Final Acceptance Certificate Submission Checklist  - Underground Utilities 71
7.27 Final Acceptance Certificate Submission Checklist  - Stormwater Facilities 72
7.28 Development Approvals Pond FAC Signoff - Checklist #8 73
7.29 Construction Completion Checklist Sheet - Sidewalk, Curbs, and Gutters 76
7.30 Construction Completion Checklist Sheet - Paved Roads and Walkways 77
7.31 Construction Completion Checklist Sheet - Lanes 78
7.32 Construction Completion Checklist Sheet - Sound Attenuation Fence & Screen Fence 79
7.33 Construction Completion Inspection Approval Sheet  - Paved Roads (Water Resources) 80
7.34 Field Inspection Sheet Construction Completion - Surface Improvements (Roads) 81
7.35 Construction Completion Certificate Submission Checklist - Paved Roads and Walkways 82
7.36 Construction Completion Certificate Submission Checklist - Sidewalks, Curbs, and Gutters 83
7.37 Construction Completion Certificate Submission Checklist - Paved Lanes 84
7.38 Construction Completion Certificate Submission Checklist - Gravelled Lanes 85
7.39 Construction Completion Certificate Submission Checklist - Sound Attenuation Fence & Screen Fence 86
7.40 Final Acceptance Inspections Approval Sheet - Paved Roads (Water Resources) 87
7.41 Final Acceptance Field Inspection Sheet - Surface Improvements (Roads) 88
7.42 Final Acceptance Certificate Submission Checklist - Paved Roads and Walkways 89
7.43 Final Acceptance Certificate Submission Checklist - Sidewalks, Curbs, and Gutters 90
7.44A Final Acceptance Certificate Submission Checklist – Paved Lanes 91
7.44B Final Acceptance Certificate Submission Checklist – Gravelled Lanes 91
7.45 Final Acceptance Certificate Submission Checklist - Sound Attenuation Fence & Screen Fence 92