Sarcee Trail bridge reconstruction

Project update

  • Phase 2 construction begins June 2 and will see reduced lanes on the Sarcee Bridge over 16 Avenue N.W. through completion of this phase.
  • Throughout construction, the clearance of the Sarcee Bridge over 16 Avenue N.W. is 4.8 metres.
  • Watch for reduced speeds in the construction area. ​
​​

Project timeline

  • Project start: Feb. 2018
  • Project completion: late Oct. 2018
​​

The construction is planned to be completed in three phases, starting with the east side of the bridge. The first phase is expected to be completed in late May, allowing crews to move onto Phase 2 in early June. There will be reduced lanes and speeds on the bridge to facilitate the construction zone. The entire project is expected to continue until late October 2018.

Motorists are reminded to adhere the posted speed limits and watch for construction workers in the area during construction.