Edmonton Trail N.E. pavement rehabilitation

Calgary Traffic Report 2016 Paving Projects


As part of The City of Calgary’s Pavement Rehabilitation Program, Edmonton Trail N.E. between Memorial Drive and 16 Avenue N.E. and 4 Street between Memorial and Edmonton Trail is scheduled for rehabilitation during the 2016 construction season. Cycle track upgrades are also scheduled to be constructed as part of this rehabilitation.

The City of Calgary would like to thank residents, businesses and commuters for their patience and understanding during the road construction process. Please observe all posted signs and speed limits to ensure the safety of commuters and construction crews.

Project Scope

  • Localized concrete sidewalk or curb and gutter repairs.
  • Localized base repairs will also occur between Memorial Drive and 16 Avenue to improve the structure of pavement.
  • Milling of the existing asphalt surface on the entire segment (between Memorial Drive and 16 Avenue N.E.)
  • Overlay with two or more layers of asphalt to provide a structurally sound and smooth surface for the design life.

Timeline

Construction is began near the end of April 2016 with concrete repairs performed along Edmonton Trail. There will be temporary traffic impacts throughout the construction season. Every effort will be made to ensure the impact of traffic movement is kept to a minimum, when possible, by working on weekends and off peak hours.
​Type of Work ​Where ​Tentative Schedule ​Traffic Impact
​Concrete repairs ​Curb and gutter, median and islands - both lanes ​End of​ April - June 2 ​Temporary lane closures at affected location during weekends and off-peak hours
​Pavement base repairs ​Select areas of pavement ​May 15 - June 2 ​Temporary lane closures at affected location during weekends and off-peak hours
​Removal of existing asphalt - milling

​Edmonton Trail

4 Street

​July

​Temporary lane closures at affected location during weekends and off-peak hours
​Paving

​Top lift from Memorial Dr. to 16 Ave.

 

​Sep. 17-18

​Temporary lane closures at affected location during weekends and off-peak hours

The City of Calgary’s contracted partners will communicate with the public and impacted businesses about the construction before it begins and on an ongoing basis throughout construction. This web page is a primary source of updated information.