Macleod Trail S.E. pavement rehabilitation

Calgary Traffic Report 2016 Paving Projects


As part of The City of Calgary’s Pavement Rehabilitation Program, Macleod Trail S.E. between 34 Avenue and 58 Avenue S.E. is scheduled for rehabilitation during the 2016 construction season.

The City of Calgary would like to thank residents, businesses and commuters for their patience and understanding during the road construction process. Please observe all posted signs and speed limits to ensure the safety of commuters and construction crews.

Prior to paving, Water Services will be completing a feedermain valve upgrade project.

Project Scope

  • Localized concrete sidewalk or curb and gutter repairs.
  • Localized base repairs will also occur between 34 Avenue and 58 Avenue to improve the structure of pavement.
  • Milling of the existing asphalt surface on the entire segment.
  • Overlay with two or more layers of asphalt to provide a structurally sound and smooth surface for the design life.

Timeline

There will be temporary traffic impacts throughout the construction season. Every effort will be made to ensure the impact of traffic movement is kept to a minimum, when possible, by working on weekends and off peak hours.
​Type of Work ​Where ​Tentative Schedule ​Traffic Impact
​Concrete repairs ​Curb and gutter, median and islands - both lanes Aug. 8-18 ​Temporary lane closures at affected location during weekends and off-peak hours
​Pavement base repairs ​Select areas of pavement ​August ​Temporary lane closures at affected location during weekends and off-peak hours
​Removal of existing asphalt - milling ​Northbound ​Aug. 19-21 ​Night work, however temporary lane closures at affected location during weekends and off-peak hours may occur
​Removal of existing asphalt - milling ​Southbound ​Aug. 26-28 ​Night work, however temporary lane closures at affected location during weekends and off-peak hours may occur
​Paving ​Northbound Aug. 21 - 28 Reduced lanes and speed reductions northbound
Paving ​Southbound ​Aug. 29 - Sep. 17 ​Single lane closure daily from 9:30 a.m. - 3 p.m.
​Clean-up ​Entire project limits ​Sep. 18 ​Various lane closures until barricades are removed

The City of Calgary’s contracted partners will communicate with the public and impacted businesses about the construction before it begins and on an ongoing basis throughout construction. This web page is a primary source of updated information.