Northeast
36 Street between Country Hills Boulevard and 80 Avenue NE
Start: 2013/04/08 5:00 AM
End: 2013/08/07 6:00 PM
Details:
5 AM April 8 to 6 PM August 7
The road is closed for the roadway between Airport Trail and Country Hills Boulevard to be reconstructed and expanded from two to four lanes. The closure will also allow the Airport Trail connections to be made to 36 Street going east out of the Airport Trail tunnel.
Motorists are advised to use Metis Trail as an alternate route.
For further information, visit the
project page.
36 Street north of Country Hills Boulevard NE
Start: 2013/04/11 10:00 AM
End: 2013/08/08 12:00 PM
Details:
10 AM April 11 to 12 PM August 8
The road is closed.
52 Street at 16 Avenue NE
Start: 2013/05/17 9:00 AM
End: 2013/05/24 3:00 PM
Details:
9 AM to 3 PM daily on weekdays from May 17 to 24
The right lane is closed in both directions. Speed is restricted to 50 km/h.
54 Avenue between 44 Street and Westwinds Drive NE
Start: 2013/05/24 12:00 PM
End: 2013/05/24 4:00 PM
Details:
12 PM to 4 PM May 24
The road is closed for the Ahmadiyya Muslim Jama'at Calgary event.
54 Avenue between 44 Street and Westwinds Drive NE
Start: 2013/05/22 5:00 PM
End: 2013/05/22 9:00 PM
Details:
5 PM to 9 PM May 22
The road is closed for the Ahmadiyya Muslim Jama'at Calgary event.
6 Street between McDougall Road and Centre Avenue NE
Start: 2013/05/16 7:00 AM
End: 2013/05/31 6:00 PM
Details:
7 AM May 16 to 6 PM May 31
The road is closed.
63 Avenue east of 36 Street NE
Start: 2013/05/22 8:00 AM
End: 2013/05/24 6:00 PM
Details:
8 AM May 22 to 6 PM May 24
The road is reduced to a single lane of alternating traffic.
Eastbound Airport Trail at 19 Street NE
Start: 2013/05/21 7:00 AM
End: 2013/05/25 6:00 PM
Details:
7 AM May 21 to 6 PM May 25
The right lane is closed. Speed is restricted to 50 km/h.
Metis Trail south of Country Hills Boulevard NE
Start: 2013/04/18 12:00 PM
End: 2013/08/08 12:00 PM
Details:
12 PM April 18 to 12 PM August 8
Speed is restricted to 50 km/h.
Northbound Centre Street between McKnight Boulevard and Thorncrest Road NE
Start: 2013/05/16 8:00 PM
End: 2013/05/24 12:00 PM
Details:
8 PM May 16 to 12 PM May 24
The right lane is closed.
Southbound 36 Street south of 26 Avenue NE
Start: 2013/06/01 10:00 PM
End: 2013/06/02 3:00 PM
Details:
10 PM June 1 to 3 PM June 2
The two left lanes are closed. Speed is restricted to 50 km/h.
Southbound 36 Street south of 26 Avenue NE
Start: 2013/05/17 8:00 PM
End: 2013/05/20 6:00 PM
Details:
8 PM May 17 to 6 PM May 20
The road is closed for LRT work.
Between 12 AM May 19 and 7 AM May 20, there will be one southbound lane open.
Traffic will be detoured to 26 Avenue to 32 Street. Delays are expected and motorists are advised to use an alternate route.
Westbound Airport Trail west of Barlow Trail NE
Start: 2013/05/13 7:00 AM
End: 2013/05/31 6:00 PM
Details:
7 AM May 13 to 6 PM May 31
The left lane is closed. Speed is restricted to 50 km/h.
Northwest
14 Street between 2 Avenue and 5 Avenue NW
Start: 2013/05/17 9:00 AM
End: 2013/05/19 8:00 PM
Details:
9 AM May 17 to 8 PM May 19
The left lane is closed in both directions.
2 Avenue between 9A Street and 10 Street NW
Start: 2013/05/08 9:00 AM
End: 2013/06/01 6:00 PM
Details:
9 AM May 8 to 6 PM June 1
The road is closed eastbound.
20 Avenue at 14 Street NW
Start: 2013/05/19 8:00 AM
End: 2013/05/19 11:00 AM
Details:
8 AM to 11 AM May 19
The left lane is closed in both directions.
20 Avenue between 7 Street and 8 Street NW
Start: 2013/05/25 7:00 AM
End: 2013/05/26 6:00 PM
Details:
7 AM May 25 to 6 PM May 26
The road is closed.
Bowness Road at 16 Avenue NW
Start: 2013/05/22 5:00 AM
End: 2013/05/23 6:00 PM
Details:
5 AM to 6 PM daily on May 22 and 23
The right lane is closed in both directions.
Bowness Road at 16 Avenue NW
Start: 2013/05/21 6:00 PM
End: 2013/05/24 5:00 AM
Details:
6 PM to 5 AM nightly from May 21 to 23
The road is reduced to one lane in both directions.
Bowness Road at 16 Avenue NW
Start: 2013/05/18 5:00 AM
End: 2013/05/21 6:00 PM
Details:
5 AM May 18 to 6 PM May 21
The right lane is closed in both directions.
Brentwood Boulevard between Branford Drive and Bell Street NW
Start: 2013/05/21 8:00 AM
End: 2013/05/24 6:00 PM
Details:
8 AM May 21 to 6 PM May 24
The road is reduced to one lane in both directions.
Centre Street at 68 Avenue NW
Start: 2013/05/23 9:00 AM
End: 2013/05/23 12:00 PM
Details:
9 AM to 12 PM May 23
The left lane is closed in both directions.
Crowchild Trail and 5 Avenue NW
Start: 2013/05/19 8:00 AM
End: 2013/05/19 11:00 AM
Details:
8 AM to 11 AM May 19
On northbound Crowchild Trail, the right lane is closed. Speed is restricted to 50 km/h.
On westbound 5 Avenue, the left lane is closed.
Eastbound 16 Avenue between 14 Street and Centre Street NW
Start: 2013/05/21 9:00 AM
End: 2013/05/21 3:00 PM
Details:
9 AM to 3 PM May 21
There will be various left lane closures.
Eastbound 16 Avenue between Bowness Road and Shaganappi Trail NW
Start: 2013/05/14 10:00 AM
End: 2013/05/23 6:00 PM
Details:
10 AM to 6 PM daily on weekdays from May 14 to 23
The left lane is closed. Speed is restricted to 50 km/h.
Eastbound 16 Avenue east of 29 Street NW
Start: 2013/05/21 9:00 AM
End: 2013/05/23 3:00 PM
Details:
9 AM to 3 PM daily from May 21 to 23
The right lane is closed. Speed is restricted to 50 km/h.
Eastbound 16 Avenue east of Crowchild Trail NW
Start: 2013/05/21 9:00 AM
End: 2013/05/24 6:00 PM
Details:
9 AM to 6 PM daily from May 21 to 24
The right lane is closed. Speed is restricted to 50 km/h.
Eastbound Crowchild Trail between Stoney Trail and Nose Hill Drive NW
Start: 2012/01/01 12:00 PM
End: until further notice
Details:
until further notice
Speed is restricted to 60 km/h on weekdays for LRT construction.
Eastbound Crowchild Trail west of Stoney Trail NW
Start: 2013/01/06 12:00 PM
End: 2013/07/21 12:00 PM
Details:
12 PM January 6 to 12 PM July 21
The left lane is closed. Speed is restricted to 60 km/h.
Eastbound Memorial Drive between 14 Street and 10 Street NW
Start: 2013/06/08 9:00 AM
End: 2013/06/08 3:00 PM
Details:
9 AM to 3 PM June 8
The right lane is closed.
Monserrat Drive west of Bowness Road NW
Start: 2013/05/24 8:00 AM
End: 2013/05/24 12:00 PM
Details:
8 AM to 12 PM May 24
The road is closed for the HD Cartwright Triathlon.
Northbound 10 Street at 2 Avenue NW
Start: 2013/05/08 9:00 AM
End: 2013/05/24 3:00 PM
Details:
9 AM to 3 PM daily on weekdays from May 8 to 24
The right lane is closed.
Nose Hill Drive at Stoney Trail NW
Start: 2012/08/09 6:00 PM
End: 2013/11/30 6:00 PM
Details:
until November 2013
The traffic signals at Stoney Trail and Nose Hill Drive have been removed. Nose Hill Drive is now closed across the Stoney Trail corridor.
Direct access from westbound Nose Hill Drive to northbound Stoney Trail and eastbound Nose Hill Drive to southbound Stoney Trail will be
maintained.
Through traffic on Nose Hill Drive will be detoured around Stoney Trail via Bearspaw Dam Road.
Access from northbound Stoney Trail to westbound Nose Hill Drive and Tuscany Hill will be via the detour along eastbound Nose Hill Drive, southbound 87 Street and Bearspaw Dam Road.
Access from southbound Stoney Trail to eastbound Nose Hill Drive will be via the detour along westbound Nose
Hill Drive, Bearspaw Dam Road and northbound 87 Street.
Access to southbound Stoney Trail from westbound Nose Hill Drive will be via southbound 87 Street, Bearspaw Dam Road and eastbound Nose Hill Drive.
Access to northbound Stoney Trail from
eastbound Nose Hill Drive will be via the detour along Bearspaw Dam Road, northbound 87 Street and westbound Nose Hill Drive.
Visit
Alberta Transportation for an illustration of the detour routes.
Sage Hill Drive between Symons Valley Road and Sage Hill Boulevard NW
Start: 2013/04/15 9:00 AM
End: 2013/06/15 6:00 PM
Details:
9 AM April 15 to 6 PM June 15
The road is closed. Traffic will be detoured to 144 Avenue.
Shaganappi Trail at John Laurie Boulevard NW
Start: 2013/05/22 9:00 AM
End: 2013/05/23 3:00 PM
Details:
9 AM to 3 PM daily on May 22 and 23
The right lane is closed northbound.
The left lane is closed southbound.
Southbound 10 Street between Gladstone Road and 3 Avenue NW
Start: 2013/05/06 9:00 AM
End: 2013/06/08 6:00 PM
Details:
9 AM to 6 PM daily on weekdays and 7 AM to 6 PM on Saturdays from May 6 to June 8
The right lane is closed.
Southbound Shaganappi Trail at John Laurie Boulevard NW
Start: 2013/05/24 9:00 AM
End: 2013/05/25 3:00 PM
Details:
9 AM to 3 PM May 24 and 8 AM to 3 PM May 25
The left lane is closed. Speed is restricted to 50 km/h.
Westbound 16 Avenue between Shaganappi Trail and Bowness Road NW
Start: 2013/05/17 6:00 PM
End: 2013/05/19 6:00 PM
Details:
6 PM May 17 to 6 PM May 19
The right lane is closed. Speed is restricted to 50 km/h.
Westbound 16 Avenue west of Sarcee Trail NW
Start: 2013/04/15 8:00 AM
End: 2013/06/17 3:00 PM
Details:
8 AM to 3 PM daily on weekdays and 8 AM to 4 PM on Saturdays until June 17
The right lane is closed for noise wall replacement. Speed is restricted to 60 km/h.
Westbound Crowchild Trail at Stoney Trail NW
Start: 2012/06/08 12:00 PM
End: until further notice
Details:
until further notice
Speed is restricted to 60 km/h on weekdays for LRT construction.
Southeast
1 Street between 4 Avenue and 5 Avenue SE
Start: 2013/04/26 7:00 PM
End: 2013/05/31 5:00 AM
Details:
7 PM April 26 to 5 AM May 31
The right lane is closed.
11 Avenue between 8 Street and Maggie Street SE
Start: 2013/05/13 7:00 AM
End: 2013/06/14 6:00 PM
Details:
7 AM May 13 to 6 PM June 14
The road is closed. Local access will be maintained.
25 Avenue between Spiller Road and Dartmouth Road SE
Start: 2013/06/01 7:00 AM
End: 2013/06/02 7:00 PM
Details:
7 AM June 1 to 7 PM June 2
The road is closed.
3 Street between 6 Avenue and 9 Avenue SE
Start: 2013/05/17 6:00 PM
End: 2013/05/21 5:00 AM
Details:
6 PM May 17 to 5 AM May 21
The road is closed.
5 Street between 6 Avenue and 8 Avenue SE
Start: 2012/08/21 9:00 PM
End: until 2014
Details:
until early 2014
The road is closed for East Village construction.
52 Street and 90 Avenue SE
Start: 2013/05/24 7:00 AM
End: 2013/05/27 5:00 AM
Details:
7 AM May 24 to 5 AM May 27
On 52 Street between 86 Avenue and 90 Avenue, the road is closed for utility work. Motorists are advised to use Barlow Trail as an alternate route.
On 90 Avenue between 52 Street and 60 Street, the road is closed for utility work.
52 Street at 126 Avenue SE
Start: 2013/05/03 7:00 AM
End: 2013/06/30 5:00 PM
Details:
7 AM May 3 to 5 PM June 30
The road is reduced to one lane in both directions for utility installation.
There will be no left turns permitted at the intersection.
52 Street between Erin Woods Drive and 50 Avenue SE
Start: 2012/09/02 10:00 AM
End: until Summer 2013
Details:
until Summer 2013
Speed is restricted to 50 km/h.
68 Street between 106 Avenue and 108 Avenue SE
Start: 2013/03/12 10:00 AM
End: 2013/05/31 7:00 PM
Details:
10 AM March 12 to 7 PM May 31
Traffic will be shifted onto a temporary detour road on the east side of 68 Street to allow for utility installations and surface upgrades. Speed is restricted to 30 km/h.
9 Avenue and 1 Street SE
Start: 2013/05/27 9:00 AM
End: 2013/05/27 3:00 PM
Details:
9 AM to 3 PM May 27
On 9 Avenue between 1 Street and MacLeod Trail, the two left lanes are closed.
On 1 Street between 8 Avenue and 9 Avenue, the left lane is closed.
9 Avenue and 1 Street SE
Start: 2013/05/22 9:00 AM
End: 2013/05/25 3:00 PM
Details:
9 AM to 3 PM daily from May 22 to 25
On 9 Avenue between Centre Street and 1 Street SE, and on 1 Street between 7 Avenue and 9 Avenue SE, there will be buses loading and unloading children in the right lanes for the Calgary International Children's Festival.
Centre Avenue west of Barlow Trail SE
Start: 2013/05/25 7:00 AM
End: 2013/05/26 6:30 PM
Details:
7 AM May 25 to 6:30 PM May 26
The road is closed eastbound.
Centre Avenue west of Barlow Trail SE
Start: 2013/05/18 7:00 AM
End: 2013/05/19 6:30 PM
Details:
7 AM May 18 to 6:30 PM May 19
The road is closed eastbound.
The left lane is closed westbound.
Eastbound 17 Avenue at 68 Street SE
Start: 2013/05/22 8:00 PM
End: 2013/05/23 6:00 AM
Details:
8 PM May 22 to 6 AM May 23
The right lane is closed.
Eastbound 6 Avenue between MacLeod Trail and 3 Street SE
Start: 2013/05/17 8:00 AM
End: 2013/05/19 6:00 PM
Details:
8 AM May 17 to 6 PM May 19
The right lane is closed.
Lake Fraser Gate at MacLeod Trail SE
Start: 2012/11/12 6:00 AM
End: until further notice
Details:
Left turns from Lake Fraser Gate to MacLeod Trail will be restricted between 6 AM and 8:30 AM daily on weekdays as part of a pilot project. Motorists should use Canyon Meadows Drive as an alternate route.
MacLeod Trail at 210 Avenue SE
Start: 2013/04/27 9:00 AM
End: 2013/05/31 6:00 PM
Details:
9 AM April 27 to 6 PM May 31
The right lane is closed northbound.
The southbound left turn bay is reduced to one lane.
Mayor's Environment Expo
Start: 2013/06/04 9:00 AM
End: 2013/06/06 3:00 PM
Details:
9 AM to 3 PM daily from June 4 to 6
- 9 Avenue west of MacLeod Trail, the right lane is closed.
- MacLeod Trail between 9 Avenue and 7 Avenue, the right lane is closed.
Northbound 52 Street south of 90 Avenue SE
Start: 2013/05/21 9:00 AM
End: 2013/05/27 5:00 PM
Details:
9 AM to 3 PM daily on May 21 and 22
9 AM May 23 to 5 PM May 27
The right lane is closed.
Northbound Blackfoot Trail south of Heritage Drive SE
Start: 2013/05/21 9:00 AM
End: 2013/06/01 5:00 PM
Details:
9 AM to 3 PM daily on weekdays and 7 AM to 5 PM on Saturdays from May 21 to June 1
The right lane is closed. Speed is restricted to 60 km/h.
Northbound Centre Street between 9 Avenue and 8 Avenue SE
Start: 2013/05/21 6:00 PM
End: 2013/05/22 6:00 AM
Details:
6 PM May 21 to 6 AM May 22
The right lane is closed.
Northbound MacLeod Trail between 25 Avenue and 17 Avenue SE
Start: 2013/05/18 7:00 PM
End: 2013/05/21 5:00 AM
Details:
7 PM May 18 to 5 AM May 21
The right lane is closed.
The ramp from northbound Deerfoot Trail to eastbound Stoney Trail / Marquis of Lorne Trail SE
Start: 2013/05/09 10:00 AM
End: 2013/07/04 6:00 PM
Details:
10 AM May 9 to 6 PM July 4
The existing eastbound off ramp is being removed and a new ramp will be built in its place. Traffic travelling from northbound Deerfoot Trail to eastbound Stoney Trail / Marquis of Lorne Trail will be re-routed to go under the Stoney Trail bridge to access the turnoff to go eastbound or westbound. Temporary traffic signals have been installed to help motorists heading east on Stoney Trail as they will have to cross the westbound lanes.
Between 10 AM and 3 PM May 9 only, the traffic signals will be in flash mode and traffic control persons will be on site to direct traffic. The traffic signals will be switched to regular timing prior to the rush hour and will remain on for the duration of the construction.
Westbound 6 Avenue between 3 Street and MacLeod Trail SE
Start: 2013/05/17 6:00 PM
End: 2013/05/21 5:00 AM
Details:
6 PM May 17 to 5 AM May 21
The two right lanes are closed.
Westbound 90 Avenue west of 52 Street SE
Start: 2013/05/17 9:00 AM
End: 2013/05/23 3:00 PM
Details:
9 AM May 17 to 5 AM May 21
9 AM to 3 PM daily from May 21 to 23
The right lane is closed.
Southwest
12 Avenue at 14 Street SW
Start: 2013/05/21 9:00 AM
End: 2013/05/24 3:00 PM
Details:
9 AM to 3 PM daily from May 21 to 24
There will be various lane closures.
13 Avenue between 2 Street and 4 Street SW
Start: 2013/04/29 7:00 AM
End: 2013/05/31 3:00 PM
Details:
7 AM April 29 to 3 PM May 31
The road is closed westbound.
2 Street between 2 Avenue and 3 Avenue SW
Start: 2013/02/03 5:00 PM
End: 2013/12/31 6:00 PM
Details:
5 PM February 3 to 6 PM December 31
The road is reduced to one lane in both directions.
20 Avenue between 2 Street and 4 Street SW
Start: 2013/05/22 6:00 AM
End: 2013/05/23 6:00 PM
Details:
6 AM to 6 PM daily on May 22 and 23
The road is closed.
4 Street between 3 Avenue and 4 Avenue SW
Start: 2013/05/21 8:00 AM
End: 2013/05/24 6:00 PM
Details:
8 AM May 21 to 6 PM May 24
The road is closed. Local access will be maintained.
61 Avenue at 1A Street SW
Start: 2013/05/18 8:00 AM
End: 2013/05/20 8:00 AM
Details:
8 AM May 18 to 8 AM May 20
The right lane is closed.
61 Avenue between Centre Street and 1A Street SW
Start: 2013/05/20 8:00 AM
End: 2013/05/21 5:00 AM
Details:
8 AM May 20 to 5 AM May 21
The road is closed.
7 Street between 4 Avenue and 8 Avenue SW
Start: 2013/05/04 6:00 AM
End: 2013/06/02 6:00 PM
Details:
6 AM May 4 to 6 PM June 2
The left lane is closed.
8 Avenue between 5 Street and 6 Street SW
Start: 2013/05/17 9:00 AM
End: 2013/05/19 7:00 PM
Details:
9 AM May 17 to 7 PM May 19
The road is reduced to one lane in both directions.
9 Avenue between 14 Street SW and 3 Street SE
Start: 2013/05/22 7:00 PM
End: 2013/05/23 5:00 AM
Details:
7 PM May 22 to 5 AM May 23
There will be various lane closures with the road reduced to a single lane where crews are working.
9 Avenue between 14 Street SW and 3 Street SE
Start: 2013/05/21 7:00 PM
End: 2013/05/22 5:00 AM
Details:
7 PM May 21 to 5 AM May 22
There will be various lane closures with the road reduced to a single lane where crews are working.
9 Avenue between 14 Street SW and 3 Street SE
Start: 2013/05/20 3:00 PM
End: 2013/05/21 5:00 AM
Details:
3 PM May 20 to 5 AM May 21
There will be alternating lane closures with the road reduced to a single lane where crews are working.
Eastbound Bow Trail / 9 Avenue between Crowchild Trail and 14 Street SW
Start: 2013/05/19 10:00 AM
End: 2013/05/19 7:00 PM
Details:
10 AM to 7 PM May 19
There will be alternating lane closures with the road reduced to a single lane where crews are working.
Motorists are advised to use an alternate route.
Fourth Street BRZ Lilac Festival
Start: 2013/05/26 5:00 AM
End: 2013/05/26 8:00 PM
Details:
5 AM to 8 PM May 26
The following closures will be in effect:
4 Street SW between 13 Avenue and 26 Avenue will be closed.
The intersection of 17 Avenue and 4 Street SW will be closed. Eastbound traffic will be detoured to 8 Street and 12 Avenue. Westbound traffic will be detoured to 11 Avenue.
Mount Royal Gate between Crowchild Trail and Richard Road SW
Start: 2013/05/21 9:00 AM
End: 2013/07/12 12:00 PM
Details:
9 AM May 21 to 3 PM July 12
The road is reduced to one lane in both directions.
Northbound 85 Street between Strathlea Avenue and 14 Avenue SW
Start: 2013/05/21 9:00 AM
End: 2013/05/21 3:00 PM
Details:
9 AM to 3 PM May 21
The right lane is closed.
Northbound Crowchild Trail at 33 Avenue SW
Start: 2013/05/17 9:00 AM
End: 2013/05/19 8:00 PM
Details:
9 AM May 17 to 8 PM May 19
The two right lanes are closed.
Old Banff Coach Road at Patterson Hill SW
Start: 2013/05/17 6:00 PM
End: 2013/05/21 5:00 AM
Details:
6 PM May 17 to 5 AM May 21
The road is reduced to one lane in both directions.
Spruce Drive between 37 Street and 38 Street SW
Start: 2013/05/18 7:00 AM
End: 2013/05/20 12:00 PM
Details:
7 AM May 18 to 12 PM May 20
The road is closed for emergency water services repairs.
The ramp from eastbound Bow Trail to northbound Crowchild Trail SW
Start: 2013/05/19 1:00 PM
End: 2013/05/19 6:00 PM
Details:
1 PM to 6 PM May 19
The exit ramp from eastbound Bow Trail to northbound Crowchild Trail / 10 Avenue will be closed.
Traffic will be detoured to westbound Bow Trail via 16 Street to connect with northbound Crowchild Trail.
The ramps from Crowchild Trail to eastbound Bow Trail SW
Start: 2013/05/19 5:00 AM
End: 2013/05/19 1:00 PM
Details:
5 AM to 1 PM May 19
The ramps from northbound and southbound Crowchild Trail to eastbound Bow Trail will be closed.
Northbound traffic will be detoured to 17 Avenue.
Southbound traffic will be detoured to 10 Avenue.
Wheels for Wells
Start: 2013/06/01 8:00 AM
End: 2013/06/01 4:00 PM
Details:
8 AM to 4 PM June 1
- 24 Street SW between Bridleridge Heights and Spruce Meadows Trail, there will be cyclists in the curb lane in both directions.
- Spruce Meadows Trail between 6 Street and 53 Street, speed is restricted to 50 km/h.
- Spruce Meadows Trail between 24 Street and 85 Street, there will be cyclists in the curb lane.
- Eastbound Spruce Meadows Trail between 37 Street and 24 Street, the right lane is closed.