17 Ave SW Construction schedule

Want to know when construction is happening in front of your business or property in 2017? Don’t be caught by surprise.


Project update | What to expect during construction
Last updated July 12, 2017

Project update

Macleod Trail to Centre Street

On July 17, after Stampede is over, crews will continue working on 17 Avenue between Macleod Trail and Centre Street. Work will continue to repair and rebuild the road on the north side of the street. This construction will require three lanes closed on 17 Avenue. One eastbound lane will remain open to accommodate business access.

Once crews have completed the road work on the north side of the street in late July, public realm improvements, including new sidewalks, street lighting and tress will begin. This will take approximately 3-4 weeks. Once this work is complete crews begin road work and public realm improvements on the south side of the street.

Centre Street to 1 Street S.W.

Starting July 17, crews will move construction west one block between Centre Street and 1 Street S.W. This road requires a full road closure, which means 17 Avenue will be completely closed to traffic at 1 Street S.W. This closure will be in place for approximately three months, while crews replace water and sanitary lines and repair the road. Vehicles and Calgary Transit bus routes #6 and #7 will be detoured onto 14 and 15 Avenues.

If you have questions, or would like to know more about the construction in 2017, please email us at cityofcalgary17@calgary.ca.



What to expect during construction

See when blocks will be fully closed to traffic (traffic lanes closed, sidewalks open) in 2017.

See the construction staging for each block, between Macleod Trail S.E. to 5 Street S.W.
The Where and when construction schedule provides more details on what work will be underway while each block is fully or partially closed.

Please note that timelines may be subject to change.

Photo Gallery - Unclassified

  • 17 Avenue S.W. Reconstruction - Construction staging: Macleod Trail S.E. to 5 Street S.W.
  • Macleod Trail S.E. to 1 Street S.E. - Stage 1: April 10 - July 2017
  • Macleod Trail S.E. to 1 Street S.E. - Stage 2: July - August 2017
  • 1 Street S.E. to Centre Street S. - Stage 1: May - July 2017
  • 1 Street S.E. to Centre Street S. - Stage 2: August - September 2017
  • Centre Street S. to 1 Street S.W. - Stage 1: June - September 2017
  • Centre Street S. to 1 Street S.W. - Stage 2: October 2017 & May 2018
  • 1 Street to 2 Street S.W. - Stage 1: July - September 2017
  • 1 Street to 2 Street S.W. - Stage 2: October 2017 & May 2018
  • 2 Street to 4 Street S.W. - Stage 1: August - October 2017
  • 2 Street to 4 Street S.W. - Stage 2: November 2017 & May - June 2018
  • 4 Street to 5 Street S.W. - Stage 1: September - October 2017

See the general approach to reconstructing 17 Avenue S.:

  • A new construction schedule
  • Utility disruptions
  • Traffic detour
  • Marketing approach
  • Next steps