17 Ave SW Construction schedule

Want to know when construction is happening in front of your business or property in 2017? Don’t be caught by surprise.


Status of 17 Ave construction project | What to expect during construction
Last updated April 18, 2017

What is the status of the 17 Avenue S.W. construction project now?

Week of April 17: construction is underway, Macleod Trail- 1 Street S.E.

Crews fenced off the construction zone, opened the driveway accesses, and began saw cutting the road. They’ll begin digging down to the water and sanitary lines near the end of the week.

Building inspections and temporary utilities: The contractor is contacting and visiting buildings to inspect the utility connections to make sure we can connect temporary utility connections when required. We are also required to do a building-condition inspection, for pre and post construction comparisons.

If you have questions, or would like to know more about the 2017 and 2018 construction schedule, please email us at cityofcalgary17@calgary.ca.



What to expect during construction

See when blocks will be fully closed to traffic (traffic lanes closed, sidewalks open) in 2017.

See the construction staging for each block, between Macleod Trail S.E. to 5 Street S.W.
The Where and when construction schedule provides more details on what work will be underway while each block is fully or partially closed.

Please note that timelines may be subject to change.

Photo Gallery - Unclassified

  • 17 Avenue S.W. Reconstruction - Construction staging: Macleod Trail S.E. to 5 Street S.W.
  • Macleod Trail S.E. to 1 Street S.E. - Stage 1: April 10 - July 2017
  • Macleod Trail S.E. to 1 Street S.E. - Stage 2: July - August 2017
  • 1 Street S.E. to Centre Street S. - Stage 1: May - July 2017
  • 1 Street S.E. to Centre Street S. - Stage 2: August - September 2017
  • Centre Street S. to 1 Street S.W. - Stage 1: June - September 2017
  • Centre Street S. to 1 Street S.W. - Stage 2: October 2017 & May 2018
  • 1 Street to 2 Street S.W. - Stage 1: July - September 2017
  • 1 Street to 2 Street S.W. - Stage 2: October 2017 & May 2018
  • 2 Street to 4 Street S.W. - Stage 1: August - October 2017
  • 2 Street to 4 Street S.W. - Stage 2: November 2017 & May - June 2018
  • 4 Street to 5 Street S.W. - Stage 1: September - October 2017

See the general approach to reconstructing 17 Avenue S.:

  • A new construction schedule
  • Utility disruptions
  • Traffic detour
  • Marketing approach
  • Next steps

Photo Gallery - Unclassified



If you have questions about the project or would like to receive project updates, feel free to email the project team: cityofcalgary17@calgary.ca