Share this page Print

90 Ave & 14 Street S.W. - SW BRT Construction

 
 

We have adjusted the signal timing at the 14 Street/90 Avenue intersection for eastbound traffic turning onto 14 Street S.W. Drivers will have more green time when turning left onto northbound 14 Street S.W. during rush hour. Crews have also painted additional lane markings at the intersection. We will keep monitoring this intersection and make adjustments as needed.

Crews are now working on excavation and piling for the underpass on the south side of 90 Avenue.

The final traffic detour maintains the existing number of lanes - three eastbound lanes and two westbound lanes on 90 Avenue. See the See the final detour at the intersection.

Click image to enlarge

Construction update

Week of October 15, 2018
UPCOMING CLOSURE: Eastbound 90 Avenue at 14 Street S.W.
 
Starting at 7 p.m. on October 19, 2018 until 6 a.m. October 22, 2018, the eastbound lanes from 90 Avenue S.W. onto 14 Street S.W. will be closed to traffic so crews can complete the installation of underground water and storm water infrastructure. The westbound lanes will be remain open for traffic.
 
Signage will be placed on 14 Street and 90 Avenue S.W. to let drivers know they should use Southland Drive S.W. as an alternate route. The access to Glenmore Landing will be open at all times from eastbound 90 Avenue S.W.
 
Construction update:
Concrete will be poured for the south bridge deck this week. Piling for the underpass, retaining walls and excavation for the storm water pump station continues.
 
Work continues at the northwest corner of the 90 Avenue and 14 Street S.W. intersection for the construction of the storm water siphon.
 
Construction of the 90 Avenue pedestrian overpass is expected to start once the underpass retaining walls are complete. They will begin with piling work on the east side of the 14 Street S.W. and 90 Avenue S.W. intersection.
 
 
The second stage of the 90 Avenue underpass construction is expected to be implemented in early December 2018. This will involve shifting traffic lanes to the south so crews can begin work on the north half of the underpass.
 
 

Upcoming detours and lane closures

Lane closures are typically scheduled between 9 a.m. and 3 p.m. There may be times when crews need to set up lane closures and detours before 9 a.m. These closures will not be in the direction of the heaviest rush hour traffic flow. Weekend closures are typically planned between 7a.m. and 7 p.m.
 

14 Street & 90 Avenue S.W. Intersection - bridge deck pour and underground utilities

Friday, October 19 - Starting at 7 p.m.

  • Eastbound 90 Avenue closed from 14 Street to the first entrance of Glenmore Landing. Drivers detour to Southland Drive.

Saturday, October 20 to Sunday October 21, 2018 (all day all night)

  • Eastbound 90 Avenue closed from 14 Street to the first entrance of Glenmore Landing. Drivers detour to Southland Drive.

Monday, October 22 - until 6 a.m.

  • Eastbound 90 Avenue closed from 14 Street to the first entrance of Glenmore Landing. Drivers detour to Southland Drive.

14 Street between Southland Drive & 90 Avenue S.W. - Road work

Monday, October 15 to Friday, October 19, 2018

  • Southbound 14 Street reduced to one lane.

Monday, October 22, October 19, 2018

  • Southbound 14 Street reduced to one lane.

Sign up for the latest Southwest BRT construction updates
Send me updates​​​​​​​​
​​​​​​​​​​​​​​​
​​​​​​​​​