Share this page Print

90 Ave & 14 Street S.W. - SW BRT Construction

 
 

We have adjusted the signal timing at the 14 Street/90 Avenue intersection for eastbound traffic turning onto 14 Street S.W. Drivers will have more green time when turning left onto northbound 14 Street S.W. during rush hour. Crews have also painted additional lane markings at the intersection. We will keep monitoring this intersection and make adjustments as needed.

Crews are now working on excavation and piling for the underpass on the south side of 90 Avenue.

The final traffic detour maintains the existing number of lanes - three eastbound lanes and two westbound lanes on 90 Avenue. See the See the final detour at the intersection.

Click image to enlarge

Construction update

Week of June 18, 2018
Upcoming Road Closure June 22 - July 4: Westbound 90 Avenue left hand Lane
A single left hand lane will be closed on westbound 90 Avenue at 14 Street S.W.​ from June 22 until approximately July 4 for ATCO to decommission some of their existing pipes. Because this work involves excavation in the closed lane, 90 Avenue will be reduced to one lane for westbound traffic. Drivers are encouraged to use Southland Drive and 24 Street S.W. as an alternate route.
 
Crews are continuing work on the excavation and piling for the underpass and the storm water pump station on the south side of 90 Avenue S.W. Road work on the center median on 14 Street S.W. between Southland Drive and 90 Avenue S.W. is in preparation for final paving.
 
Piling for the underpass, retaining walls and excavation for the storm water pump station will continue on the south side of 14 Street and 90 Avenue S.W. intersection. Crews will start pouring the concrete walls for the underpass in the coming weeks. Construction of underground stormwater and sanitary utilities will start in a few weeks at the intersection of 14 Street and 90 Avenue S.W.
 
Traffic lanes on 14 Street S.W. between 90 Avenue S.W. and Southland Drive S.W. will be shifted in July. Northbound traffic lanes are scheduled to shift during the week of July 9, 2018, and the southbound traffic is scheduled to switch the week of July 16, 2018.
 

Upcoming detours and lane closures

Lane closures are typically scheduled between 9 a.m. and 3 p.m. There may be times when crews need to set up lane closures and detours before 9 a.m., but these closures will not be in the direction of the heaviest rush hour traffic flow.

14 Street between Southland Drive & 90 Avenue S.W. - road work, underground utilities and concrete.

Monday June 18, 2018

  • Southbound and northbound 14 Street reduced to one lane.

Tuesday June 19, 2018

  • Southbound and northbound 14 Street reduced to one lane.

Wednesday June 20, 2018

  • Southbound and northbound 14 Street reduced to one lane.

Thursday June 21, 2018

  • Southbound and northbound 14 Street reduced to one lane.

Friday June 22, 2018

  • Southbound and northbound 14 Street reduced to one lane.

Saturday June 23, 2018

  • Northbound 14 Street reduced to one lane.

Monday June 25, 2018

  • Southbound and northbound 14 Street reduced to one lane.

Sign up for the latest Southwest BRT construction updates
Send me updates​​​​​​​​
​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​