Share this page Print

Construction updates - SW BRT Construction

 
 

Construction has started on the Southwest BRT. Crews will be working in sections along the route at different times through the construction season. The City is taking steps to minimize the impact of construction to residents and commuters by maintaining the existing number of lanes.

Lane closures are typically scheduled between 9 a.m. and 3 p.m. There may be times when crews need to set up lane closures and detours before 9 a.m. These closures will not be in the direction of the heaviest rush hour traffic flow. Weekend closures are typically planned between 7a.m. and 7 p.m.

To stay up to date with where crews are working sign up for updates.

Construction schedule

  • ​Glenmore Trail S.W.: May 2018 - September 2018
  • 14 Street Heritage Drive to 75th Ave S.W.: July 2019 - September 2019
  • 14 Street ​90th Ave to Heritage Drive S.W.: May 2018 - September 2019
  • 90th Ave & 14th St S.W. Intersection: ​March 2018 - October 2019
  • 14 Street ​Southland Drive to 90th Ave S.W.: April 2018 - July 2019
  • ​Woodbine roundabout and terminus station: Spring 2018 - Fall 2018
 

Construction areas for Southwest BRT



Glenmore Tr S.W.

Crews have started work on the bus only ramp


Heritage Dr to 75th Ave S.W.

Crews have started work on underground utilities.


90th Ave to Heritage Dr S.W.

Crews have started construction at the intersection



90 Ave & 14 St S.W. intersection

Work continues on the piling and excavation at this intersection


Southland Drive to 90th Ave S.W.

Crews have started construction on the 14 Street & Southland Dr. S.W. intersection


Woodbine roundabout and terminus station​

This work is being done in conjunction with Water services and will start in Spring 2018

 
Sign up for the latest Southwest BRT construction updates
Send me updates​​​​​​​​
 
​​​​ ​​​​​​​​​​​​​​​​​