Share this page Print

Southland Dr to 90th Ave S.W. - SW BRT Construction

 
 ​

The work at the intersection of 14 Street S.W. and Southland Drive is part of an intersection improvement.

The City is taking steps to minimize the impact of construction to residents and commuters. Lane closures required for construction should be completed in off peak times. The construction staging between Southland Drive and 90 Avenue is shown to the right.

Click image to enlarge

Construction update

Week of December 10, 2018

The Southland Drive and 14 Street S.W. intersection is now complete and operating in its final capacity. The base lift paving for the transitway in this area is also completed and the top lift for the transitway is scheduled for the summer of 2019. Minor grading works will continue in the N.W. corner and is expected to be completed next week.

Crews have completed the final tie-in of the storm water siphon at the northwest corner of the 90 Avenue and 14 Street S.W. intersection. Work continues on the south section of the vehicle bridge deck in preparation to shifting traffic to the second stage of the detour in order to begin work on the north half of the vehicle bridge. The south underpass retaining walls are currently underway, as well as the piling for the underpass and excavation for the storm water pump station. Piling has been completed for the 90 Avenue S.W. pedestrian overpass in the northwest corner of the 90 Avenue and 14 Street S.W. intersection and will begin on the east side of 14 Street S.W. Utility relocations and removals on the east side of 14 Street S.W. at the 90 Avenue S.W. intersection are ongoing.

The second stage of the 90 Avenue underpass construction detour is expected to be implemented in early January 2019. This will involve shifting traffic lanes to the south, onto the new 90 Avenue vehicle bridge so crews can begin work on the north half of the underpass.

 

Upcoming detours and lane closures

Lane closures are typically scheduled between 9 a.m. and 3 p.m. There may be times when crews need to set up lane closures and detours before 9 a.m. These closures will not be in the direction of the heaviest rush hour traffic flow. Weekend closures are typically planned between 7 a.m. and 7 p.m.

14 Street between Southland Drive & 90 Avenue S.W. - Road work

Monday, December 10 to Saturday, December 15, 2018

  • Southbound 14 Street S.W. reduced to one lane just south of 90 Avenue S.W.
  • Northbound 14 Street S.W. reduced to two lanes just north of 90 Avenue S.W.

Monday, December 17, 2018

  • Southbound 14 Street S.W. reduced to one lane just south of 90 Avenue S.W.
  • Northbound 14 Street S.W. reduced to two lanes just north of 90 Avenue S.W.

Sidewalk Closure: Southland Drive & 14 Street S.W.

  • The sidewalk on the northeast corner of Southland Drive and 14 Street S.W. is now open for pedestrians.

Sign up for the latest Southwest BRT construction updates
Send me updates​​​​​​​​
​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​ ​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​
​​​​​