Airport Boundary Metering Project

About the project

The City of Calgary will be installing water meters at service connection points to monitor water supply to airport lands. There are 11 locations identified where meters will be installed.

The water meters being installed are larger than a residential meter but work the same way. The new meters will monitor flows through the water distribution pipes and record the information.

  • Work will be completed at 11 locations around the boundary of the YYC Calgary International Airport.
  • Installation of the new meters involves shutting down the existing water main, removing small sections of pipe, installing an underground concrete vault, and installing new piping to reconnect to the existing system. The meter will be located inside the vault. A control panel will be installed on the surface to provide power and monitor the meter readings.
  • Construction fencing will be in place for the duration of this project.
  • Multiple sites will be under construction at one time.

Construction Impacts

  • Road detours and lane closures will be required for these installations.
  • Some businesses may experience water service interruptions. We will contact those who are impacted by water service interruptions directly to provide more details.
  • Work will be performed from 7 a.m. until 10 p.m., six days a week. Work may occur on holidays and Sundays in order to meet the project schedule.
  • Equipment may be stored adjacent to each site.
  • The temporary staging areas and access routes will be restored to original condition or better.

Project schedule

Work is scheduled to begin in late March and continue for three months.

Project locations

Click on the blue boxes to view specific construction details on the map.

Water Meter installation at Calgary Airport W1 W2 W3 W5 W6 W8 W13 W14 W15 W16 W17

 

Location W1 - 11 Street N.E. & Aero Gate N.E.

This site is located in the north bound lanes of 11 Street N.E., south of the intersection with Aero Gate N.E.

Construction Dates: Early May 2017 for approximately two (2) weeks.

Traffic Impacts: Northbound traffic on 11 St NE will be impacted at Aero Gate N.E. Suggested detour route is 64 Avenue N.E. to Aero Drive N.E. Locations W1 and W2 will not be constructed at the same time.

Water Service Impacts: No water service impact anticipated. If you experience a water service interruption, please contact 311.

Location W2 - Aero Drive N.E., east of 11 Street N.E.

The meter will be installed in an existing vault which is located part way up the hill in the south-west bound lanes of Aero Drive N.E. Minor excavation work will be required.

Construction Dates: Late June 2017 for approximately one (1) week.

Traffic Impacts: South-west bound traffic on Aero Drive N.E. will be impacted but northbound traffic will be maintained. Suggested detour route is Aero Gate N.E. to 11 Street N.E. Locations W1 and W2 will not be constructed at the same time.

Water Service Impacts: No water service impact anticipated. If you experience a water service interruption, please contact 311.

Location W3 - 11 Street N.E. & Aviation Park N.E. / 53 Avenue N.E.

Construction completed.

Location W5 - Aviation Road & McKnight Blvd. N.E.

Construction completed.

Location W6 - McTavish Road & McKnight Blvd. N.E.

Construction completed.

Location W8 - Pegasus Road & Barlow Trail N.E.

This site is located west of the intersection of Pegasus Road & Barlow Trail N.E., in the westbound lane of Pegasus Road N.E.

Construction Dates: Early June 2017 for approximately two (2) weeks.

Traffic Impacts: Traffic from southbound Barlow Trail N.E. to westbound Pegasus Road N.E. will be impacted. Recommend alternative access from McCall Way N.E. Minimal or no impact is expected for southbound Barlow Trail N.E.

Water Service Impacts: No water service impact anticipated. If you experience a water service interruption, please contact 311.

Location W13 - Freeport Blvd. N.E. & Barlow Trail N.E.

This site is located in the southeast part of the intersection of Barlow Trail N.E. and Freeport Blvd. N.E.

Construction Dates: Late May 2017 for approximately two (2) weeks.

Traffic Impacts: Major disruptions to northbound Barlow Trail N.E. and eastbound Freeport Blvd. N.E. The traffic accommodation plan is in development. Locations W13 and W14 will not be constructed at the same time.

Water Service Impacts: Water meters will be installed starting May 25. Please see project notice for traffic detour information. If you experience a water service interruption, please contact 311.

Location W14 - 100 Avenue N.E. & Barlow Trail N.E.

This site is located in the northeast part of the intersection of Barlow Trail and 100 Avenue N.E.

Construction Dates: Late May 2017 for approximately two (2) weeks. 

Traffic Impacts: Major disruptions to northbound Barlow Trail N.E. and eastbound 100 Avenue N.E. The traffic accommodation plan is in development. Locations W13 and W14 will not be constructed at the same time.

Water Service Impacts: No water service impact anticipated. If you experience a water service interruption, please contact 311.

Location W15 - On 19 Street N.E., south of Airport Trail N.E. and north of Aero Drive N.E.

This site is located in the northwest part of the intersection of 19 Street N.E. and Aero Drive N.E.

Construction Dates: Mid May 2017 for approximately two (2) weeks.

Traffic Impacts: Two- way traffic will be maintained on 19 Street N.E. but access will be reduced to one lane in each direction. Coordination with the Calgary Airport Authority is ongoing to minimize impacts to airport access. The traffic accommodation plan is in development and this information will be updated if there are changes.

Water Service Impacts: No water service impact anticipated. If you experience a water service interruption, please contact 311.

Location W16 - West of 19 Street N.E. & South of Airport Trail N.E.

Construction completed.

Location W17 - East of intersection of Airport Trail & Deerfoot Trail N.E., near Aero Crescent N.E.

This site is located on the south side of Airport Trail N.E., between 19 Street N.E. and Deerfoot Trail.

Construction Dates: June 2017 for approximately two (2) weeks.

Traffic Impacts: No major traffic impact anticipated. Speeds may be reduced or a lane may be closed on eastbound Airport Trail N.E. when required to facilitate safe entrance/exit to the site. The traffic accommodation plan is in development and this information will be updated if there are changes.

Water Service Impacts: No water service impact anticipated. If you experience a water service interruption, please contact 311.