Share this page Print

Inglewood sanitary trunk project

Ongoing Project Activity - March 2019

Construction of the Inglewood Sanitary Trunk is continuing, with work on the 11 Street S.E. section of the trunk. Crews will be onsite to perform utility locate and relocate work around 17 Avenue SE and 11 Street SE by the CP Rail overpass. Shaft construction will continue shortly thereafter.From now until the middle of May, there will be intermittent closures of one northbound lane along 11 Street S.E from 9 a.m. - 3 p.m. Monday to Friday, and on weekends as needed.​

About this project

When water runs down a sink, drain or toilet, it becomes wastewater. Calgary has a system just for wastewater, moving it by gravity and pumps to one of three wastewater treatment plants.

Calgary’s system is made up of 5,491 km of sanitary pipes. The Inglewood Sanitary Trunk will involve the construction of 4 km of sanitary pipe which will provide additional wastewater capacity needed for projected flow from existing and future development.

Frequently Asked Questions

What is the proposed route for the Inglewood Sanitary Trunk?


Click on image to enlarge and view microtunnelling route.

What are the potential impacts to residents?

Traffic impacts

There will be temporary deoutrs and access restrictions during this project. If detours or restrictions are needed, every effort will be made to work with residents to maintain access for local traffic

Dust

Dust levels will be low during microtunneling. There will be some dust during the open cut construction. The City will respond to dust through street cleaning/sweeping as needed.

Noise

Noise levels during construction
Click to view larger image.