Macleod Trail SW Feedermain Valve Upgrade Project

About the Project

The City of Calgary Water Services will be replacing and removing a series of aging pipes and valves at five sites on Macleod Trail SW between 50 Ave. SW and 34 Ave. SW.

Construction begins July 18, 2016 and continues until early August. This is a result of Water Services' regular operational maintenance program to ensure system reliability.

Project Schedule

The work being done on each site will vary from 2 to 12 days, depending on the scope of work required. Hours are from 6:30 am until 9:30 pm each day.

Work Sites and Schedules

Southbound Macleod Trail at 45 Ave. S.W. Construction dates: July 18- 25
Construction work: multiple valve replacements and removals

Traffic closures:

  • Full closure southbound Macleod Trail at 45 Ave. S.W.
  • No access to and from 45 Ave. SW
Southbound Macleod Trail at 38 Ave. S.W. Construction dates: July 18- 22
Construction work: valve removal and pipe repair/feedermain washout valve reconfiguration
 

Traffic closures:

  • Full closure southbound Macleod Trail at 38 Ave. S.W.
Northbound Macleod Trail at 34 Ave. S.W. Construction dates: to be completed July 31
Construction work: 16" valve replacement
Southbound Macleod Trail at 34 Ave. SW Construction dates: July 23 - 26
Construction work: valve removal and replacement

Traffic closures:

  • Full closure of southbound Macleod Trail
Southbound Macleod Trail at 34 Ave. SW Construction dates: July 26 - 28
Construction work: valve replacement
 

Traffic closures:

  • Single northbound land at 34 Ave. S.W.
Southbound Macleod Trail at 42 Ave. S.W. Construction dates: July 25 - 31 (tentative)
Construction work: triple valve replacement

Traffic closures:

  • Full closure of southbound Macleod Trail at 42 Ave. S.W.
  • No right turn from 42nd Ave. to Macleod Trail S.W.
Northbound Macleod Trail at 46 Ave. S.W. Construction dates: July 30 (morning) - completed July 31 (evening)
Construction work: valve replacement
Southbound Macleod Trail at 50 Ave. S.W. Construction dates: July 26 - 31
Construction work: 30" feedermain valve replacement

Traffic closures:

  • 2 outside lanes southbound Macleod Trail
  • 1 westbound lane on 50 Ave S.W.
Northbound Macleod Trail at 50 Ave. S.W. Construction dates: Aug 1 - Aug 2 (evening)
Construction work: 6" feedermain valve replacement

Project details

Valves are necessary for isolating the water line so that Water Services crews are able to shut down the feeder main with minimal service disruption to customers during a water main break.

Stay Informed

Please refer to this page for regular updates or contact 311 for project contact information. Refer to Calgary Roads for closures and detours.