12 Mile Coulee NW Update

Attached here is a drawing showing what exists and what is proposed for 12 Mile Coulee NW.  For 2017, half of the road will be twinned from approximately Tusslewood Dr to 300m south of Tuscany Way.  The remaining road will be twinned to 80 Ave in 2018

The high level construction schedule is as follows:
•         Tusslewood Drive N.W. South to Tuscany Way N.W.
o   Pathway complete by July 10th
o   Pre-grading, communications, tie-in to existing – August 2017
o   ENMAX relocation Sept 1 – Oct 10
o   Retaining walls and surfacing – Oct to Mid-November
o   Landscape and Guardrail – Late November
•         Tuscany Way N.W. South to 100 metres North of Watermark Villas
o   Pre-grading and detour -  June 26 to July 8th
o   Underground – Week of July 10th
o   Surfacing Mid July to end of August
•         100 metres North of Watermark Villas South to 80th Avenue
o   2018 Construction
•         80th Avenue – Surfacing
o   to be completed by July 8th


Stay connected! Sign up here to receive Councillor Ward Sutherland's monthly e-newsletter.

This content represents the personal views and opinions of the Councillor and should not be taken as a statement of policy of The City of Calgary. The inclusion of any external content does not imply endorsement by The City of Calgary.

Access City Services

For non-emergency service

Contact311

311 connects citizens with non-emergency services, 24 hours a day, seven days a week.

Download the app
 

Available for iPhone in App Store and Android in Google Play store.

Request service online

Submit a request

For City news and information search Calgary.ca and follow the City on social media.