NEWS RELEASE - APRIL 24, 2015

Shaganappi Pedestrian Overpass Construction

TEMPORARY ROAD CLOSURE – SHAGANAPPI TRAIL

Constrction of the bridge is progressing. The contractor is adjusting the hanger rods in preparation for installation of the concrete span. During this procedure, Shaganappi Trail between Crowchild Trail and Northland Dr./Dalhousie Dr. will be temporarily closed during non-peak traffic hours.

The installation is scheduled for this weekend. A second weekend may be required to complete installation. Details about future road closures will be available once dates have been confirmed.

Temporary Road Closures
Fri. April 24: 9 PM – 6 AM
Sat. April 25: 9 PM – 6 AM
Sun. April 26: 9 PM – 5 AM

Variable message boards will be placed in several nearby locations to notify motorists of the closure and detour routes. Attached hereis a visual of the designated traffic detour.
All efforts will be made to minimize disruptions to residents by providing notification and scheduling closures around non-peak traffic hours.

If you have any questions regarding this project, please contact 3-1-1.

 

NEWS RELEASE - March 16, 2015

Due to the wind speeds last Saturday, the lift of the bridge arch was postponed until Sunday evening.  Undeterred by the snow, the lift began at 9:30 p.m. and was in place by 11:30 p.m.
The City will update the project webpage with information and post the time-lapse video.  

Reminder that this weekend, the road closures for Shaganappi Trail will take place for installation of the concrete panels on the main span.  This activity is still dependent on wind speeds being below 25 km/hr.

Shaganappi Trail Road Closures

Fri. March 20:       9 PM – 6 AM
Sat. March 21:      9 PM – 6 AM
Sun. March 22:     9 PM – 5 AM

Shag Update

NEWS RELEASE - March 10, 2015

Shag

Transportation Infrastructure has an update for the Shaganappi Trail Pedestrian Overpass Project. The dates and times are now scheduled to close Shaganappi Trail NW to complete work on the main span of the bridge overpass. The lifting of the steel arch is scheduled for weekend one.  Placement of concrete panels on the main span is scheduled for weekend two.  Both of these activities are dependent on wind speeds being below 25 km/hr.

During this installation, Shaganappi Trail between Crowchild Trail and Northland Dr. / Dalhousie Dr. will be temporarily closed during off peak hours.  Variable message boards will be placed in several nearby locations to notify motorists in advance of the closure and detour routes.

Weekend 1
Fri. March 13:       9 PM – 6 AM
Sat. March 14:      9 PM – 6 AM
Sun. March 15:     9 PM – 5 AM

Weekend 2
Fri. March 20:       9 PM – 6 AM
Sat. March 21:      9 PM – 6 AM
Sun. March 22:     9 PM – 5 AM

Resolution

The delay in erection was due to two interior steel beams that required shifting to fit in place with the concrete ramps.  The modification is almost complete and construction will continue as scheduled. Area stakeholders and businesses have been notified about the upcoming lift dates and lane closures of Shaganappi Trail NW.

The City of Calgary will not be responsible for costs associated with the modification. The City will continue to work diligently with the consultant Hatch Mott Macdonald and the contractor PCL to ensure the final product is built as intended. The bridge is scheduled to be open to the public by mid-May. 

NEWS RELEASE - January 2, 2015

Originally, The City of Calgary planned to close Shaganappi Trail from January 16th -18th to lift the steel span of the bridge, however, this was postponed because the steel structure did not fit onto the pillars as expected.

The contractor and consultant confirmed that there were two steel crossbeams that conflicted with the pre-constructed bridge ramps. As a result, there will be modifications required in order to ensure a correct fit to secure the installation. Until this work is completed, the second temporary closure of Shaganappi Trail will be postponed. Lifting the bridge span will be postponed until March, date to be determined. While the postponement affects the initial proposed lane closures, it does not impact the scheduled opening timeline of spring 2015

The City is working with consultants and contractors to solve these challenges. The budget project remains at $5.9 million. Stakeholders will be notified when the new lift date is scheduled, potentially in March, 2015.
 





 

This content represents the personal views and opinions of the Councillor and should not be taken as a statement of policy of The City of Calgary. The inclusion of any external content does not imply endorsement by The City of Calgary.

Access City Services

For non-emergency service

Contact311

311 connects citizens with non-emergency services, 24 hours a day, seven days a week.

Download the app
 

Available for iPhone in App Store and Android in Google Play store.

Request service online

Submit a request

For City news and information search Calgary.ca and follow the City on social media.