Ward 1 News: Snow and Ice Update, Feb 20

  • Share

Ward 1 official website

Roads Snow and Ice Control (SNIC) operations update for February 20, 2018:

P1 routes and cycle tracks are completed. P2 routes will be completed today and we will continue to work on our steps, walks and pedestrian overpasses. Currently, there are 28 dedicated staff and 13 pieces of small equipment working on pedestrian facilities and there are 31 sanders and 8 graders working on roadways. We are on Day 3, hour 3 of the 7 Day Snow Plan.  

Our priority system consists of Priority 1 - 4. The current status is:

•        P1 - 100% complete
•        P2 - 96% complete
•        Cycle Track - 100% complete
•        Bike Lanes - 84% complete
•        P3 and P4 – 6% complete
•        Steps and Walks – 40% complete

Click here to see completed routes and current progress.

The cost so far to respond to Snow Event #21 was $1.4M.

The 7-day forecast is calling for chances of flurries today and mainly sunny conditions during the week.

Get municipal and community updates, sign up for the Ward 1 report at

This content represents the personal views and opinions of the Councillor and should not be taken as a statement of policy of The City of Calgary. The inclusion of any external content does not imply endorsement by The City of Calgary.

Access City Services

For non-emergency service


311 connects citizens with non-emergency services, 24 hours a day, seven days a week.

Download the app

Available for iPhone in App Store and Android in Google Play store.

Request service online

Submit a request

For City news and information search and follow the City on social media.