Ward 11 News: 61st Avenue Greenway Corridor and Pedestrian Bridge Fall Updates

  • Share

Ward 11 official website 

61st Avenue Greenway Corridor

Construction for the Greenway Corridor continues. Please see the proposed alternate routes map to help you avoid delays on your commute. The scope of the project has changed, corridor improvements will only take place on 61 Avenue S.W. from Macleod Trail to the LRT tracks. There will be no construction on 61 Avenue S.W. from the LRT tacks to Centre Street.

 

Project Timeline
Conceptual/preliminary design - Completed Spring 2015
Public Open House – April 26, 2015
Detailed design – Completed Fall 2015
Information Sessions – April 30, May 3 & 5, 2016
Construction – Anticipated for May 2016
Substantial Completion – Fall 2016
Landscaping, paving – Spring 2017

 
 

61st Avenue Pedestrian Bridge

 

Construction on the accompanying Pedestrian Bridge is now underway. You can expect to see work on the west side of Macleod Trail as crews begin foundation work for the new bridge.

Project timeline
Preliminary Design – Completed fall 2015
Detailed Design – summer 2016
Construction – September 2016
Completion – late 2017

 


For more information visit:

- 61st Avenue SW Greenway Corridor
- 61st Avenue SW Pedestrian Bridge

 
 
 

 
 
 
This content represents the personal views and opinions of the Ward Councillor and should not be taken as a statement of policy of The City of Calgary. The inclusion of any external content does not imply endorsement by The City of Calgary.
 
​​

Access City Services

For non-emergency service

Contact311

311 connects citizens with non-emergency services, 24 hours a day, seven days a week.

Download the app
 

Available for iPhone in App Store and Android in Google Play store.

Request service online

Submit a request

For City news and information search Calgary.ca and follow the City on social media.