17 Ave SW construction project

Project update

Postponed: The signal work that was scheduled at the Macleod Trail/17 Avenue S.E. intersection on Sunday, January 28, between 7 a.m. and 6 p.m., has been postponed until further notice.

We are now planning the 2018 construction schedule in January and February. Our goal is to have the 2018 construction schedule prepared and publicly available as soon as possible.

The Avenue between Macleod Trail and 14 Street S.W. is open for on-street parking. The #6 and #7 buses are back to running their regular routes. While there will be some minor traffic signal and street light work happening throughout the winter, parking and traffic impacts will be minimum. We'll post the work here, as it's confirmed.

If you have questions, or would like to know more about the project, please email us at cityofcalgary17@calgary.ca

Remaining work from 2017

The following work that was originally scheduled for the 2017 construction season at the locations detailed below, is now scheduled for spring 2018 (April-June). This work will require single-lane closures and some on-street parking closures.

  • Macleod Trail - 2 Street S.W.: replace the temporary asphalt in sidewalks with permanent concrete
  • 1 Street - 2 Street S.W.: finish tree planting on both sides and minor electrical work on south side

The City will contact business prior to all work starting, and we will be working with businesses to minimize the disruption as much as possible.

 

Stay up to date on 17 Ave's construction schedule

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​