88 St S.E. extension - between Stoney Trail and 196 Ave

Project Scope

By extending 88 Street N.E., we're building new connections and supporting future communities and development. Here's what the extension will do for Calgary's southeast:

  • Extends 88 Street S.E. from Stoney Trail to 196 Avenue S.E.
  • Doubles the capacity of the road with two northbound and two southbound lanes
  • Accommodates future development
  • Reduces congestion on 52 Street S.E., once 196 Avenue S.W. is connected
  • Adds a second access to the Mahogany community and access to the new Rangeview communities, east of 88 Street S.E.

Project design

Click to enlarge image

Project background

This improvement to Calgary's southeast allows new community development, east of the new Seton Town Centre. The four-lane 88 Street S.E. road is the first phase of a future six-lane road. It extends south 2.6 kilometers, from the interchange at Stoney Trail and Highway 22X, connecting to 196 Avenue S.E.

Schedule

  • Q4 2019: Complete design and tender contract
  • Q1 2020: Award contract
  • Q2 2020: Begin construction
  • Q4 2020: Complete construction of roadway
  • Q2 2021: Complete remaining construction, including landscaping

Project budget

Budget approved: $23.5 million.

  • Budget was approved by Council, as part of One Calgary's Service Line "Streets".
​​​​​​​​