2017 Complete Streets Corridor Project

Bowness Phase 2

Upcoming Activities:

  • The City of Calgary will be installing an additional guard over Shouldice Bridge for bike protection. The work will be completed by late October. The install takes approximately 3-4 weeks so expect some delays as there will be construction flaggers during the working hours who will direct traffic.
  • North side concrete work has been completed along the corridor. Angled parking has been restored on the north side. Currently working to pour the rest of the concrete swales on south side in the next 2 weeks. Angled parking should be opened shortly once the concrete is fully cured.
  • The underpass work continues along the north side of Bowness Road. The north side of the underpass will be open to pedestrians shortly with temporary guard rails. The south side of the work with retaining walls will begin shortly after. The completion of the underpass is estimated to be completed mid-October.
  • The traffic calming measure along Bowwood Drive is estimated to be completed mid-October.
  • 5 medians will be placed along Bowness Road and this will commence when the curb work has been completed.
  • Pavement rehabilitation is anticipated to be completed in the beginning of October, with line painting and signage to follow, weather permitting.
  • During Pavement rehabilitation, there will be disruptions to traffic and parking temporarily.