2013 Surface Overlay Paving Program



​​

It's only February, but it's still a good time to think about road paving this summer. That is because the City of Calgary's Roads, Construction Division has released its 2013 Surface Overlay Paving schedule.

Paving work generally alternates between the north and south portions of the city each year in order to keep fair distribution of funding and to maximize efficiency. In addition, extensive evaluation of pavement conditions plays a part in determining which roadways are selected for surface rehabilitation.

In Ward 14, parts of Deer Run and Parkland will be undergoing paving. Sections of Macleod Trail will also be undergoing a different kind of paving called "microsurfacing." The paving schedule shown below along with frequently asked questions will be posted on Calgary.ca before the paving program starts in June. As always, the Roads department will continue to communicate road closures through 311, Calgary.ca, and the City's social media channels.

Please note that the schedule is subject to change due to weather and emergency road work.

Ward 14 paving schedule: July - October 2013 *

undefined: Street undefined: Starting cross street undefined: Finishing cross street
undefined: Street: 146 Avenue S.E. undefined: Starting cross street: Deer Run Boulevard S.E. undefined: Finishing cross street: Parkland Boulevard S.E.
undefined: Street: Parkglen Crescent S.E. undefined: Starting cross street: Parkland Boulevard S.E. undefined: Finishing cross street: Parkland Boulevard S.E.
undefined: Street: Parkland Way S.E. undefined: Starting cross street: Parkridge Drive S.E. undefined: Finishing cross street: Parkridge Drive S.E.
undefined: S​treet: Parkridge Crescent S.E. undefined: Starting cross street: Parkridge Drive S.E. undefined: Finishing cross street: Parkridge Drive S.E.
undefined: Street: Parkridge Drive S.E. (east leg) undefined: Starting cross street: Parkland Boulevard (north leg) undefined: Finishing cross street: Parkvalley Drive S.E.
undefined: Street: Parkridge Green S.E. undefined: Starting cross street: Parkridge Drive S.E. (east leg) undefined: Finishing cross street: Parkridge Drive S.E. (south leg)
undefined: Street: Parkridge Road S.E. undefined: Starting cross street: Parkridge Drive S.E. undefined: Finishing cross street: Parkridge Drive S.E.
undefined: Street: Parkside Crescent S.E. undefined: Starting cross street: Parkside Drive S.E. undefined: Finishing cross street: Parkside Drive S.E
undefined: Street: Parkvalley Drive S.E. undefined: Starting cross street: Parkland Boulevard S.E. undefined: Finishing cross street: Parkland Boulevard S.E.
undefined: Street: Parkview Crescent S.E. (west leg) undefined: Starting cross street: Parkview Way S.E. undefined: Finishing cross street: Parkview Way S.E.
undefined: Street: Parkvista Crescent S.E. undefined: Starting cross street: Parkvalley Drive S.E. undefined: Finishing cross street: Parkvalley Drive S.E.
undefined: Street: Parkside Drive S.E. undefined: Starting cross street: Parkland Boulevard (north leg) undefined: Finishing cross street: Parkland Boulevard (south leg)


Microsurfacing

undefined: Street undefined: Starting cross street undefined: Finishing cross street
undefined: Street: Macleod Trail S.E. undefined: Starting cross street: Sun Valley Boulevard S.E. undefined: Finishing cross street: 194 Avenue S.E.


* Please note: The paving season runs from June to October, exact dates of scheduled paving can be found on Calgary.ca.in spring, 2013. Paving schedules are subject to change due to weather and emergency road work.​

Categories:

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null