Station area | Location | Project type | Impact | Status | End date | Details |
---|---|---|---|---|---|---|
Station area: 2 Avenue S.W. | Location: 3 Avenue between 3 Street S.W. and 2 Street S.W. | Project type: Telus utility construction | Impact: Road closure Lane closure Parking removal Sidewalk closure Cycle track impact Noise Congestion and traffic delays |
Status: Active | End date: Late February 2023 | Details: See the detailed detour and construction map |
Station area: 2 Avenue S.W. | Location: 4 Avenue between 1 and 2 Streets S.W. | Project type: Telus utility construction | Impact: Lane closure(s) Parking removal Noise Congestion and traffic delays |
Status: Active | End date: Spring 2023 | Details: See the detailed detour and construction map |
Station area: 7 Avenue S.W. | Location: 1 Street S.W. between 6 and 8 Avenue S.W. and 7 Avenue between 1 Street S.W. and 2 Street S.W. | Project type: ENMAX utility construction | Impact: Intersection closure Parking removal Bus stop relocation Noise |
Status: Active | End date: Mid-to-late February 2023 | Details: See ENMAX website |
Station area: 7 Avenue S.W. | Location: 1 Street S.W. between 5 and 4 Avenue S.W. | Project type: ENMAX utility construction | Impact: Lane closures Parking removal Congestion and traffic delays Noise |
Status: Active | End date: Late January 2023 | Details: See ENMAX website |
Station area: 7 Avenue S.W. | Location: 5 Avenue between 3 and 1 Street S.W. | Project type: ENMAX utility construction | Impact: Lane closures Parking removal Bus stop relocation Noise |
Status: Active | End date: Summer 2023 | Details: See ENMAX website |
Station area: 4 Street S.E. | 12 Avenue S.E. between Olympic Way and 6 Street S.E.
|
Project type: BDURP utility construction | Impact: Lane closure Road closure Parking removal Noise |
Status: Active | End date: May 2023 | Details: See the detailed detour and construction map |
Station area: Ogden | Location: 78 Avenue S.E. | Project type: Road widening and underpass project | Impact: Noise Lane restrictions and rerouting Restriction for walking/ wheeling Heavy machinery operating in the area |
Status: Project is dependent on start of Phase 1 construction | End date: TBD | Work is planned to build an underpass at 78 Ave. S.E. to accommodate the planned street access termination at 69 Avenue S.E. at the CP rail crossing. The existing access will be rerouted to the underpass. This work will make way for the future Ogden station. |