16 Avenue over Barlow Trail N.E. Bridge Rehabilitation Project

Built in 1978, the 16 Avenue N.E. bridge is a two span box girder bridge that carries three eastbound and three westbound traffic lanes across Barlow Trail N.E. Various parts of the bridge are deteriorating due to age and are in need of rehabilitation. This project will be tendered in the fall of 2020 and construction is planned for Spring/Summer of 2021.

Project update - November 27, 2020

This project will be tendered in December 2020.

Construction Timeline

May 1 – Oct 30, 2021

Scope of Work

The rehabilitation work on the bridge structure will include:

  • New concrete median barrier and westbound side barrier.
  • Replacement of expansion joints and bearings.
  • Girders, deck, abutment and wing wall repairs.
  • New concrete overlay.

Expected Traffic Impact

Construction will be done in stages.

  1. Two lanes eastbound and westbound on 16 Ave will remain open for traffic with one lane in each direction closed.
  2. Two lanes northbound and southbound on Barlow Tr will remain open for traffic with one lane in each direction closed.

Budget

$5 million

Project timelines

  • Tender: December 2020
  • Construction: May 2021 – Oct 2021