88 Street S.E. extension - between Stoney Trail and 196 Avenue

Project update - October 7, 2020

In order to take advantage of the good weather we’ve been experiencing this fall, crews are planning to place gravel and begin paving during Thanksgiving weekend (Oct. 11 and 12). This extra weekend work will allow crews to complete as much construction as possible this fall before colder conditions set in.

  • Earthworks are completed
  • Main stormwater installation is scheduled to be finished in fall 2020
  • Paving in the Transportation/Utility Corridor (TUC) is planned for fall 2020
  • Final road completion is scheduled for Summer 2021

About the project

By extending 88 Street S.E., we're building new connections and supporting future communities and development. Here's what the extension will do for Calgary's southeast:

  • Extends 88 Street S.E. from Stoney Trail to 196 Avenue S.E.
  • Doubles the capacity of the road with two northbound and two southbound lanes. See roadway design.
  • Accommodates future development
  • Reduces congestion on 52 Street S.E., once 196 Avenue is connected
  • Adds a second access to the Mahogany community and access to the new Rangeview communities, east of 88 Street S.E.

Project design

Click to enlarge image

Project background

This improvement to Calgary's southeast allows new community development, east of the new Seton Town Centre. The four-lane 88 Street S.E. road is the first phase of a future six-lane road. It extends south 2.6 kilometers, from the interchange at Stoney Trail and Highway 22X, connecting to 196 Avenue S.E.

Schedule

  • 2019: Complete design and tender contract
  • Early 2020: Award contract
  • July 2020: Begin construction
  • Summer 2021: Complete remaining construction, including landscaping

Project budget

Budget approved: $23.5 million.

  • Budget was approved by Council, as part of One Calgary's Service Line "Streets".
​​​​​​