Woodlands Woodbine Community Drainage Improvements

The City's Community Drainage Improvements Program works to reduce overland flooding in areas throughout Calgary.

We completed drainage studies to identify solutions for communities frequently hit by flooding due to extreme rainfall. Solutions include adding storm drainage pipes, increasing the size of pipes, and adding wet or dry storm ponds to manage stormwater.

In recent years, Woodlands, Woodbine, Cedarbrae and Braeside have experienced an unusually high number of high volume rainfall events.

These communities have a storm level service of a one-in-five year rainfall event or less, which was the standard when these communities were first built. That means that there is now a 20 percent chance (or greater) the storm system will not handle yearly rainfall events causing local flooding.

Drainage improvements for these communities target a 1-in-50 year level of service. Once upgrades are in place, there will be a two percent chance in any given year that rain events would overwhelm the storm system.

Project Gallery

​​​​​​​​​​​​​​​​​


Braeside dry pond

The City of Calgary installed a new dry pond in the fields located east of the John Ware and St. Benedict schools​.

This dry pond will greatly reduce flooding during heavy rain events, specifically the flooding that occurs at the intersection of Southland Drive S.W. and Braeside Drive S.W.

Construction of the dry pond was completed in Spring 2019.

Community benefits

Overall vehicle and pedestrian safety will be improved, traffic congestion reduced and emergency vehicle access unimpeded by flooding.

John Ware and St. Benedict schools received a new soccer field and a baseball diamond.


24 Street Storm Trunk Diversion

Phase 1 - 4: Summer 2020 (see figure image on right)

  • Storm sewer diversion - The storm sewer installation along 24 Street S.W. is complete.
  • Surface improvements – Paving works and upgrades to the intersection of 24 Street and Woodpark Boulevard S.W. are complete. 

Bebo Grove Storm Pond

A new storm pond was constructed in the Bebo Grove day use area of Fish Creek Provincial Park.

The pond is a hybrid wet pond-wetland where wetland water levels will vary with the seasons and amount of rainfall.

A new asphalt trail has been constructed around the south perimeter of the pond to connect with existing trails in Fish Creek. Construction is complete.

Community benefits

The storm pond will allow for storage of stormwater during rain events and improve the quality of the water discharged to Fish Creek by separation and settlement of suspended solids.

Newly created picnic areas and lookouts surrounding the pond will provide spaces for park users to enjoy the improved aesthetics of the Bebo Grove area and the wet pond will attract more bird and wildlife species.

Bebo Grove Storm Pond renderings  

Secondary Improvements

This project spans Cedarbrae, Braeside, Woodlands and Woodbine, and aims to implement localized improvements in order to alleviate existing flooding issues.

In 2017, The City identified several high priority sites for flood mitigation, including the installation of inlet control devices at multiple locations, with construction to continue this year.

These sites were identified and prioritized by means of modelling, data collection, field checks and registered 311 complaints, with more sites to follow this year.

Construction impacts

  • Spill route improvements improve overland flow paths and reduces the depth of ponding at spill points in the local neighbourhood. 
  • Storm sewer diversion include the installation of storm pipes and catchbasins to divert, increase capacity and alleviate surcharging.
  • Installation of inlet control devices (ICD's) used to address local storm sewer surcharge problems by restricting the amount of stormwater captured by catchbasins.
  • ICD's help reduce water backing up into basements and sewer overflows since capacity is better controlled at the pipe inlet, and the water remains in the catchbasin or above ground.

Bow Crescent NW

Installation of a catchbasin and connecting pipe will begin late August or early September 2020. The sidewalk will also be extended in front of 7203, 7227 and 7223 Bow CR NW.

There will be access and parking restrictions during the course of construction and we will be reaching out to the residents prior to construction commencing.

St. Cyril School Playfields

Construction of a berm at the east edge of the St. Cyril school playfields will begin in summer 2021. The berm will help to reduce stormwater drainage flowing east from the playfields and alleviate flooding of properties.

Inlet Control Devices (ICD’s)

Installation of ICD’s will also begin September 2020.