Share this page Print

Bleacher permits

​​​​​​ Apply online​​

24 hours a day, seven days a week using your City of Calgary myID


Costs

$25 + GST application fee, plus

$3 + GST per lineal metre


Timelines

Applications must be received a minimum of 90 days in advance.


Related information

ePermits FAQ

 

 

A permit is required to construct bleachers for events like the Calgary Stampede or a street festival. 

Regulations

The following rules apply for the installation of bleachers:

  • Only 20% of the parade route is permitted to have bleacher seating.
  • No bleachers may be installed in front of surface parking lots, at Transit bus stops and zones and in front of construction sites.
  • The bleachers must be 0.3 metres away from the edge of the curb. There must be one metre of space between the back of the bleachers and the building behind.

How to apply

Bleacher permit applications must be received at least 90 days in advance.

The application must include:

  • Name, address, telephone number and contact person of the company or organization requesting the space for bleacher-style seating.
  • A plan showing the construction details of the bleachers, which has been signed stamped by a professional engineer (structural) licensed to practice in Alberta.
  • Specific locations and length in lineal metres where bleachers will be installed.
  • Certificate of general liability insurance in the amount of $2 million, naming The City of Calgary as additionally insured.

Once you register for a myID, you will be able to log into ePermits to apply. If you need help or additional explanation when using the ePermits website, please see the ePermit frequently asked questions.

Permit costs

The cost of the bleachers permit is $25 + GST application fee, plus $3 + GST per lineal metre of sidewalk used.​​