Yes
Share this page Print

Bowmont West Fish Habitat Compensation


About the Project

Following the 2013 flood, The City undertook a number of projects to repair and reinforce riverbanks along the Bow River. These projects helped protect critical City infrastructure but in some cases had negative impacts on sensitive fish habitat along the river.

In order to appropriately compensate for the loss of fish habitat, The City identified a number of sites that could supplement lost fish habitat. One of these sites is at the west side of Bowmont Park. Construction and fish compensation started in July 2018 and will last until the end of the year.

The site is located at the west side of Bowmont Park and the fish compensation work will take place on the north bank of the Bow River. Work will entail:

  • Reopening historic side channels.
  • Re-establishing flow to the side channels, through excavation and re-contouring, to provide year-round connectivity from and to the main channel of the Bow River.
  • Constructing additional fish habitat structures using large trees and boulders.
  • Re-planting of all areas that were disturbed by the flood.
  • Adding new channel banks that will have native plants and grasses.
  • Replacement of the existing (North) pedestrian bridge with a longer single span bridge.

Project update - November 12, 2018

Construction crews have completed the excavation of the main channel are currently excavating other channels throughout the park. This work includes salvaging vegetation to be re-planted within the construction site.

The pedestrian bridge was removed in early September and work to set the foundation for the new bridge has been completed. The new bridge is scheduled to be installed at the end of November.

Construction crews will continue with excavation work in the channels on the west side of the CPR bridge through November and December.

Photo Gallery - Unclassified

  • Bowmont Park - East End
  • Bowmont Park - After excavation
  • Bowmont Park - Pedestrian Bridge Removal
  • Example of a fish compensation project in Quarry Park: after construction.
  • Example of a Fish Compensation project in Quarry Park: before construction.
  • Bowmont Fish Compensation project: Excavated river gravels being placed on island point bar.
  • Bowmont Fish Compensation project: upper isolated area.

Construction impacts

  • Closure of the pathway along the north side of the river (see map below). Closure of the pedestrian bridge connecting the park with Bowness and the south side of the river.
  • Pathway closures and detours and clearly marked and will be in place until December 2018.
  • River access will be restricted to allow for construction.
  • The west parking lot and adjacent off-leash area is closed and used for a construction staging area.
  • Approximately 12 trees will be removed to allow for construction. These will be used in the fish habitat compensation and replaced with approximately 3,000 trees and shrubs as part of the project.

Bowmont West Fish Habitat Enhancement Project
Click on image to enlarge

If you have any questions, or would like more information, please contact 311.

​​​