Subscribe to our newsletterIn August Scotia Place really started to take shape with the following work being done on site:
First concrete slab was poured for the main concourse (ground level).
Approximately 25% of concrete has been poured for the mezzanine level.
Waterproofing was completed for the community arena.
Excavation continued for the parkade and the N.E. corner of the site.
The foundation for 1 of 4 temporary shoring towers was poured for the steel roof installation.
Started digging the foundation that will support the restaurants on the west side (along Stampede Trail S.E.).
Progress made on S.W. stormwater tank.
Watch the progress video