78 Avenue Grade Separation and Ogden Pedestrian Tunnel
The 78 Avenue Grade Separation and Ogden Pedestrian Tunnel was a large-scale early works project
Scope of work
The overall scope of work included constructing a pedestrian tunnel at 72 Avenue SE, a vehicle underpass at 78 Avenue SE, and upgrading a portion of 78 Avenue from Ogden Road east to the Canadian Pacific Kansas City (CPKC) rail line, including new utilities and roadworks to support long-term infrastructure needs. On the east side of the embankment, a new roundabout connecting to Ogden Dale Road was also constructed to create a new entrance in and out of the industrial area.
As an early works project, this work enhances transportation and pedestrian safety in the area and supports the future construction of the Green Line SE Project.
The Green Line alignment will run parallel and west of the current CPKC rail line in Ogden, with its own bridge to cross 78 Avenue SE. The Ogden Station will be located near 72 Avenue SE.
Start Date: June 2023
Completion Date: July 2025
Construction Partner:
Design Partner:
78 Avenue area
Other work included installation and upgrades of stormwater infrastructure and other utility installations, including a manhole at Ogden Road and 78 Avenue SE, and landscaping and sidewalk improvements.
Once the underpass is open towards the end of July, , 78 Avenue SE will become the new connection between Ogden and the industrial area east of the CPKC rail tracks. However, 78 Avenue SE will not be designated as a truck route.
72 Avenue area
A pedestrian tunnel near 72 Avenue SE has been built to connect the future Ogden Station to Ogden Dale Road SE. This tunnel will remain closed until the future Ogden station opens. The tunnel is currently fenced for safety reasons.
69 Avenue
Once the underpass at 78 Avenue SE is open to traffic, 69 Avenue SE at the CPKC tracks will be closed permanently.
78 Avenue SE will become the new connection between Ogden Road and Ogden Dale Road SE.