Current construction
Find and learn about construction happening now for Green Line. Narrow down your search results by using filters or view construction impacts and notices to see what type of work is being done in your area.
Viewing 7 articles.
George Moss Park redevelopment
Geotechnical drilling
Demolition of Artpoint, Mustard Seed and Green Leaf Buildings
Eau Claire Market and River Run Condos demolitions
Beltline Downtown Utility Relocation Project (Third-party Shallow Utilities)
78 Avenue Project
North Central Bus Rapid Transit (BRT) improvements
Impacts and notices
Find out what areas are impacted by Green Line construction and the type of work being done.
Last updated: August 28, 2024
Downtown
To make way for the Green Line stations and tunnel under 2 Street S.W., work is underway to move underground utilities (e.g., Telus, ENMAX) away from 2 Street and into adjacent streets and avenues.
Location | Project type | Impact | Status | When | Details |
---|---|---|---|---|---|
Barclay Parade |
Permanent Closure |
|
|
week of August 12, 2024 | |
1 Street S.W. and Centre Street S. |
Shaw cable pulling (night work) |
|
|
September 3 - 11, 2024 (weekdays) | |
5 Avenue, 6 Avenue, and 2 Street S.W. |
CDHI Utility Relocation – Phase I - Weekdays |
|
|
September 4 - 13, 2024 | |
5 Avenue, 6 Avenue, and 2 Street S.W. |
CDHI Utility Relocation – Phase I - Weekends |
|
|
September 6 - 9, 2024 September 13 - 16, 2024 Closures will begin Friday at 8 pm and end Monday at 5 am
|
Beltline East
To make way for the Green Line station and tunnel under 11 Avenue S.E., we are moving underground utilities (storm water and sanitary) into 12 Avenue S.E.
Beltline West
To make way for the Green Line station and tunnel under 11 Avenue S.W., we are relocating and realigning existing third-party utilities away from 11 Avenue S.W. into adjacent streets, avenues and alleyways.
Location | Project type | Impact | Status | When | Details |
---|---|---|---|---|---|
104 and 106 11 Avenue S.W. |
Demolition |
|
|
August 6 - October 2024 | |
1 Street S.W. and Centre Street S. |
Shaw cable pulling (night work) |
|
|
September 3 - 11, 2024 (weekdays) |
Ogden
Work is planned for this area to make way for the future Ogden Station.
Location | Project type | Impact | Status | When | Details |
---|---|---|---|---|---|
78 Avenue S.E. from 25 Street S.E. to 27 Street S.E. and Ogden Dale Road S.E. |
Phased closures for road upgrades |
|
|
April 2024 - September 2024 | |
Ogden Dale Road S.E. upgrades |
Green Line roadworks |
|
|
May 15, 2024 - September 2024 | |
78 Avenue S.E. and Ogden Road S.E. lane closures |
78 Avenue S.E. upgrades |
|
|
July 29, 2024 - mid-August | |
Ogden Dale Road S.E. upgrades |
Green Line roadworks |
|
|
August 2 - mid-August 2024 | |
78 Avenue S.E. west of Ogden Road |
78 Avenue S.E. upgrades |
|
|
August 19 - for six weeks | |
78 Avenue S.E. |
Secant pile wall |
|
|
October 2023 to late December 2024 | |
78 Avenue S.E. Near 72 Avenue S.E. 69 Avenue. S.E |
78 Avenue S.E. vehicle tunnel and a pedestrian tunnel near 72 Avenue S.E. |
|
|
Estimated to be completed by summer 2025 |
See the 78 Avenue Project page |
Ramsay
Work is planned for this area to make way for the future Ramsay/Inglewood Station.
Location | Project type | Impact | Status | When | Details |
---|---|---|---|---|---|
1038 17 Avenue S.E. |
Demolition |
|
|
August 6 - October 2024 |
Centre St. N.
Work is planned for this area to make way for future Green Line stations.
Location | Project type | Impact | Status | When | Details |
---|---|---|---|---|---|
1612 Centre Street N. |
Demolition |
|
|
August 6 - October 2024 |