114 Ave SE and Barlow Trail Piling

Contract Status
- A Request for Proposals was posted on April 4, 2025.
- Submission deadline was May 15, 2025.
- Contract was awarded to Graham Infrastructure Ltd.
Just south of Douglas Glen station, the Green Line will be elevated as it crosses 114 Avenue and Barlow Trail S.E. This package of work is to prepare the area for construction of the elevated guideway.
Scope of work
The scope of work includes drilling concrete piles, utility relocation and road realignment (grade/base/pave).