114 Ave SE and Barlow Trail Piling

Just east of Douglas Glen station, the Green Line will be elevated as it crosses 114 Avenue and Barlow Trail S.E. This package of work is to prepare the area for construction of the elevated guideway.

Scope of work

The scope of work includes drilling 22 concrete piles, including six abutment piles and 16 pier piles, utility relocations, and road realignment work, including widening medians for the piers that will be constructed to support the elevated guideway.

Location

114 Avenue and Barlow Trail S.E.

Start Date: 
July 2025
Anticipated Completion Date:
June 2026
Construction Partner:

Images

Piling rig on site in October 2025
Piling rig on site in October 2025
Piling rig on site in October 2025
Piling rig on site in October 2025
Piling rig equipment on site in October 2025
Piling rig equipment on site in October 2025
Personnel and equipment on site in October 2025
Personnel and equipment on site in October 2025
Personnel on site in October 2025
Personnel on site in October 2025