Search Close

114 Avenue and Barlow Trail SE Piling and Road Reconfigurations

Just east of Douglas Glen station, the Green Line will be elevated as it crosses 114 Avenue and Barlow Trail SE. This contract was to prepare the area for construction of the elevated guideway.

Scope of work

The scope of work included drilling and installing 22 concrete piles (six abutment piles and 16 pier piles), relocating utilities and completing road realignment upgrades, including widening medians along Barlow Trail SE.

Location

114 Avenue and Barlow Trail SE

Start date: July 2025
Completion date: July 2026
Construction partner:

Milestone Status
Demo existing road infrastructure (i.e., medians, curbs, etc.)  Completed
Piling Completed
Utility work  Completed
New road reconfigurations and infrastructure Completed
New asphalt Completed

Images

Looking west at 114 Avenue SE in May 2026.
Looking west at 114 Avenue SE in May 2026.
Looking north on the east side of Barlow Trail SE in May 2026. Three piles are visible in the foreground sticking out of the ground, which will eventually support a large pier that will support the elevated guideway.
Looking north on the east side of Barlow Trail SE in May 2026. Three piles are visible in the foreground sticking out of the ground, which will eventually support a large pier that will support the elevated guideway.
Looking south at utility work underway in the middle of 114 Avenue SE in May 2026.
Looking south at utility work underway in the middle of 114 Avenue SE in May 2026.
Looking north at the intersection of 114 Avenue and Barlow Trail SE in May 2026. A wider median was constructed in the middle of Barlow Trail on the south side of the intersection to make room for the large piles that will eventually support the piers that will support the elevated guideway.
Looking north at the intersection of 114 Avenue and Barlow Trail SE in May 2026. A wider median was constructed in the middle of Barlow Trail on the south side of the intersection to make room for the large piles that will eventually support the piers that will support the elevated guideway.
Looking west at the intersection of 114 Avenue and Barlow Trail SE in May 2026.
Looking west at the intersection of 114 Avenue and Barlow Trail SE in May 2026.
Piling rig on site in October 2025.
Piling rig on site in October 2025.
Piling rig on site in October 2025.
Piling rig on site in October 2025.
Piling equipment on site in October 2025.
Piling equipment on site in October 2025.
Personnel and equipment on site in October 2025.
Personnel and equipment on site in October 2025.
Personnel on site in October 2025.
Personnel on site in October 2025.