Search Close

Maintenance and Storage Facility Grading and Site Servicing

As part of the Green Line, The City will construct a maintenance and storage facility (MSF) north of 126 Avenue S.E., between 40 Street S.E. and 52 Street S.E.

(Image: Maintenance and storage facility site)

The MSF is a large garage where light rail vehicles are cleaned, maintained and serviced. This summer we’ll begin preparing the site for construction, so the MSF is ready to house Green Line’s fleet of light rail vehicles once they start arriving.

Scope of Work

This work addresses the initial grading and site servicing works for the MSF.

Location

126 Avenue S.E., between 40 Street S.E. and 52 Street S.E.

Start Date:
June 2025
Anticipated Completion Date:
November 2025
Construction Partner: 
KLS Earthworks & Environmental

Images

An excavator loads an articulated dump truck with topsoil in September 2025
An excavator loads an articulated dump truck with topsoil in September 2025
A bulldozer pushes topsoil in September 2025
A bulldozer pushes topsoil in September 2025
A grader and bulldozer on site in September 2025
A grader and bulldozer on site in September 2025
Utility installation work in September 2025
Utility installation work in September 2025
Utility installation work in September 2025
Utility installation work in September 2025