114-Barlow Elevated Guideway

Contract Status

Scope of Work

The scope of work includes but is not limited to the following:

  • Single elevated guideway at 114 Avenue and Barlow Trail SE (approximately 570 metres) including abutments, piers, straddle bents, pre-cast girders, and a bridge deck (excluding piling)
  • Construction of Mechanically Stabilized Earth walls for the approaches to the guideway
  • Civil works including drainage and grading works
  • Temporary work including all site management responsibilities as required to deliver permanent work, including environmental works where applicable
  • Coordination with shallow utilities
  • Interface with the pile foundation and roadway contractor will be limited to the following completed and transferred work items: construction of pile foundations for the elevated guideway piers; roadway work affected by pile foundation construction; rehabilitation and grading of alignment property impacted by pile foundation activities; and utilities.