78 Avenue LRT Bridge
The new 78 Avenue LRT bridge was built parallel to the Canadian Pacific Kansas City (CPKC) railway line to carry future Green Line trains over 78 Avenue SE. The bridge builds on the 78 Avenue Grade Separation and Ogden Pedestrian Tunnel project completed in 2025, which created a new connection between 78 Avenue SE and Ogden Dale Road SE through a roundabout on the east side of the railway line.
Scope of work
Construction of the bridge began in October 2025, with Graham focusing primarily on material procurement, construction planning and other preparations through the remainder of the year.
Graham mobilized to the site in early spring 2026 to begin site preparation, erosion and sediment control measures, and demolition of existing road infrastructure. Crews then installed piles and constructed the foundations, retaining walls and bridge abutments that support the crossing.
In August, seven precast concrete girders, each weighing approximately 32,000 kilograms, were installed over 78 Avenue to form the main structural support for the bridge. A concrete bridge deck was then constructed over the girders, creating the future Green Line LRT crossing.
Final activities included installing railings, completing finishing work and cleaning up the site, leaving the bridge ready for track installation during a future stage of Green Line construction.
Location
| Milestone | Status |
|---|---|
| Site preparation and road infrastructure demolition | Completed |
| Pile installation and foundation work | Completed |
| Bridge abutment construction | Completed |
| Concrete girder installation | Completed |
| Bridge deck construction | Completed |