East Belvedere Feeder Main

Project status – November 2025

Construction for Phase 2A (east of Stoney Trail) has begun. We are currently in the process of hiring a contractor for the Phase 1 portion of the feeder main and expect construction to begin in fall 2025.

Community Information Session on November 12

Join us at our drop-in information session led by the Memorial Drive Extension team where you can learn more about both projects and speak with members of our teams.

Event details

  • Date: Wednesday, Nov. 12, 2025
  • Time: 4:30 to 7:30 p.m.
  • Location: Eastside City Church - 1320 Abbeydale Drive SE, Calgary
  • Everyone is welcome to attend – no registration is required.  

If you have accessibility needs or require accommodations to participate, please contact us in advance so we can support your attendance.

Project timeline

  • Construction - Begins fall 2025 – complete fall 2026

Related projects

Memorial Drive Extension Project
The City of Calgary is extending Memorial Drive east from Abbeydale and Applewood Park, over Stoney Trail and connecting to 84 Street E. 

Project background

The City of Calgary is building a new 2-kilometre-long feeder main which is an essential piece of water infrastructure that will bring clean and reliable drinking water to current and future development within the East Belvedere community.

The feeder main is being constructed in phases.

  • Phase 1 includes the installation of a feeder main along Memorial Drive from 68 Street S.E. to 84 Street S.E. and then eastward along a future extension of Memorial Drive.
  • Phase 2a, where construction also starts this fall, includes the portion from 84 Street S.E. to 100 Street S.E. along the future extension of Memorial Drive.
  • Phase 2b, which was completed this spring (2025) includes the portion on 100 Street S.E. on the future extension of Memorial Drive travelling south to 17 Avenue S.E.

Construction for Phase 1 and Phase 2a begins this fall and is scheduled to be complete in one year. The first section of construction takes place in the grassed area east of Memorial Drive. 

Project maps

Project map
Click image to enlarge.

Construction impacts

  • Residents will notice heavy truck traffic and noise in the area.
  • Construction hours for this project are, generally, from 7 a.m. to 7 p.m.
  • The contractor will take steps to limit the amount of dust in the work area.
  • The City does not expect vibration impacts from construction to affect private properties.


This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null