Connecting people to places MAX Green improvements

Making transit along Centre Street more predictable and comfortable, so everyday trips feel easier, safer and less stressful.

Project overview

We are continuing to make improvements along the Centre Street/Harvest Hills Boulevard corridor, Calgary’s busiest transit corridor. More than 30,000 people use it every day. From downtown to 160 avenue north, these upgrades help you spend less time in traffic, count on your trip and move through the city more easily.

How this improves your trip

  • Faster travel times

    Bus-only lanes and traffic signal priority help buses move past congestion, so your trip is quicker and more consistent.

  • More reliable service

    Fewer delays and more predictable travel times make it easier to plan your day.

  • Safer access to transit

    Improved crossings and walking and wheeling connections make it easier and safer to reach your stop.

MAX Green is part of Calgary’s long-term transit plan, helping connect people to jobs, school and services, now and in the future.

Project location

The MAX Green bus rapid transit improvements run from downtown along Centre Street to 160 Ave. N.E.

Ward 3: North Calgary
Ward 4: North Central Calgary

Ward 7: Centre City and inner‑city areas

Aerial view of map showing the MAX Green route from Northe Pointe to 28 Ave with locations marked for MAX Green improvements. Future scope of work includes north of North Pointe and south of 28 Ave.

Project phase

Latest updates

September 2026

Beginning in the Fall of 2026, the next milestone of improvements will include:

  • Improvements at the 78 Avenue N.E. bus loop
    A better bus loop layout and an improved break space for transit operators, supporting smoother service throughout the day.
  • Improved break space at North Pointe Transit Terminal
    Improving the break space for Transit Operators in the Terminal next to Country Village Way N.E.

Further work planned for 2027 includes:

  • New bus-only lane from 28 Avenue N.E. to 38 Avenue N.E.
    Giving buses their own space through a busy stretch, helping reduce delays and improve travel times.
  • A continuous bus-only lane through the 42–43 Avenue area
    Creating a longer, uninterrupted section where buses can move and enter the existing bus-only lane more reliably.
  • Changes at the McKnight Boulevard intersection
    Reconfiguring the intersection and extending the northbound bus-only lane to 54 Avenue, so buses can move through more efficiently.
  • Bus lane upgrades near Beddington Trail
    Extending north and southbound bus lanes to and from existing bus gates and adjusting traffic lanes to help buses move through this area more easily.
  • Extended bus-only lanes (Country Hills Boulevard  to Panatella Boulevard)
    This long stretch of bus-only lane helps keep transit moving in a growing area. A new left-turn lane into the North Pointe Park and Ride will make it easier and safer for transit accessing the North Pointe Terminal.

View maps to see the improvements we're making. Click on an image to open a larger version. Zoom in to see more detail.

Timeline

We’ve been making improvements to transit along Centre Street since 2020. Click into the timeline below to learn about each phase of improvement.

current-item

Category Icon and Label

2026+ Corridor upgrades

Start Date | End Date

Building new bus-only lanes, creating safer crossings, making key intersection changes and improving break spaces for Transit Operators.

past-item

Category Icon and Label

2025 New and improved stations, shelters and bus lanes

Start Date | End Date

Built eight new bus stations from 28 Avenue to Country Hills Boulevard. Built new platforms and shelters, bus-only lanes, intersection improvements and landscaping.

past-item

Category Icon and Label

2024 Design and early improvements

Start Date | End Date

Completed engineering design for short-term improvements. 

past-item

Category Icon and Label

2022 Park and Ride enhancement

Start Date | End Date

Completed North Pointe Park & Ride enhancements.

past-item

Category Icon and Label

2020-2021 Planning & functional study

Start Date | End Date

Completed North Central Bus Rapid Transit (BRT) functional planning study. Conducted public engagement to help inform short, medium and long-term improvements.

Construction

Construction may begin later this year in limited areas and resume in 2027. More detailed information will be shared in the spring of 2027. 

Minimizing construction impacts

Construction is part of building a better city, but we know reliable access and safe travel matter to our community. We are working hard to reduce impacts to people and businesses wherever possible.

  • Off-peak work schedule

    Planning work outside busy times to limit delays and disruption.

  • Maintained businesses access

    Keeping entrances accessible so customers can continue to visit.

  • Temporary transit stops

    Adjusting stop locations so your trip stays on track.

  • Clear detour signs

    Guiding you around construction with clear, visible routes.

Outreach and engagement

Public input helped shape MAX Green, including station locations, access improvements and construction planning.

  • Public information sessions were held in 2023 and 2024.
  • Earlier engagement (2020-2021) informed long-term plans.

Reports and presentations

Budget

2026 - 2027 improvements: $20 million

Contact

If you have questions or feedback about the project:
Email: MAXGreen@calgary.ca