Caution | State of Local Emergency declared

The City has declared a State of Local Emergency to respond to the COVID-19 pandemic. Wear a mask and get vaccinated.

COVID-19 Information Get vaccinated

Downtown Flood Barrier & Eau Claire Promenade

Project update - Fall 2021

Community Impacts & Schedule

Fall look ahead:

  • October & November:
    • Sheet piling is expected between Reconciliation Bridge and Centre Street until late October. Sheet Piling will move west as sections are completed. Piling is expected into December.
    • Drilled piles installed near the Eau Claire Lagoon for the observation deck.
    • Construction of the Centre Street Ramp abutments and installation of concrete piles.
    • Instream work under the Centre Street Bridge for the new retaining walls and pathway underpass.
    • Foundations for the stoplog flood mitigation systems (removable flood walls) at the pathway connection openings.

Sheet piling schedule:

  • Reconciliation Bridge to Centre Street: September – October
  • Centre Street to 2 Street S.W.: November
  • 2 Street S.W. to Jaipur Bridge: late November - December

Expected timeline: The above schedule is subject to change based on weather or other unforeseen circumstances.

The Downtown Flood Barrier and Eau Claire Promenade construction contract was awarded to Graham Construction, and the construction is well underway.

In early August, a detour was installed on Riverfront Avenue to support the closure of the Bow River Pathway and RiverWalk. With the detour and fencing are in place, site prep, demolition, and groundworks was completed to prepare for the installation of the flood barrier sheet pile. As part of the site preparation, we worked to salvage and transplant plants from RiverWalk.

With the removal of the Centre Street Bridge Ramps and the instream work started, installation of the sheet piles has started. These piles are vital to creating the flood barrier that will help protect downtown, Chinatown, East Village and Eau Claire from future flood events. The work is underway on the east end of the project at Reconciliation Bridge and will move west towards Centre Street. It will connect with the flood mitigation measures in Eau Claire Plaza and the new Jaipur Bridge. Sheet piling is expected to be ongoing throughout the fall.

Crews are also drilling the piles required for the Centre Street Ramps and the observation deck that overlooks the Eau Claire Lagoon, near the new Jaipur Bridge. This work will tie into the Eau Claire Promenade and connect the projects in the area.

We are constantly monitoring and adjusting the piling to ensure we are within mandated ranges for noise and vibration.

Construction in Eau Claire

To ensure Calgarians can safely visit and enjoy the area, you will see construction fences, pathway detours, and construction activity in the Eau Claire, Bow River Pathway, and RiverWalk area. Please follow the signs.

For up-to-date information and more detail, please visit our construction and detours webpage. Our website will be updated throughout construction to keep you informed about getting around and what to expect in Eau Claire.

About the projects

Downtown Flood Barrier

Protecting Calgarians from floods is a top priority for our city, and we're doing so while enhancing the Eau Claire area at the same time. We're implementing flood mitigation measures from Calgary's Flood Resilience Plan approved by Council in 2017.  These include flood barriers and stormwater improvements to ensure Calgary is protected against a 2013-level flood on the Bow and Elbow Rivers. The Downtown Flood Barrier will extend from The Peace Bridge to Reconciliation Bridge and lower the risks of flooding in the downtown, Chinatown, East Village and Eau Claire communities. 

Eau Claire Promenade

The Eau Claire Promenade extends from The Peace Bridge eastwards to the Reconciliation Bridge. Our goal is to extend the work we did at West Eau Claire Park to create a safe, efficient and beautiful riverfront promenade and cycle network that integrates flood protection into a space that connects Calgary’s downtown with the Bow River.

Our goals for the Promenade focus on:

A space for the City and Community

  • Accommodate all users for all of Calgary
  • Connect people to the Bow River
  • Build a vibrant centre city riverfront
  • Design a diversity of social spaces for mental well-being
  • Promoting active, healthy lifestyles Incorporate strategies for year-round healthy, active lifestyles – a better space for walking, jogging, biking, etc.
  • Provide a continuous, safe and accessible riverfront promenade
  • Designate efficient pathways for safe alternate modes of transportation like scooters

Environmental Responsibility

  • Preserve the natural environment by protecting most of the existing trees and plants along the river
  • Achieve multiple cost benefits through durable and beautiful design solutions

Flood Protection and Resilience

  • Integrate flood protection into the public realm improvements
  • Increase resilience for Eau Claire, the Downtown Core and future infrastructure projects

Both the Downtown Flood Barrier and Eau Claire Promenade projects are coordinated with the overarching Eau Claire Area Improvements.

Renderings & progress images

请滚动至页面底部,然后使用Google Translate 改变文本的语言。如果您没有看到Google Translate 的选项,请尝试使用其他网页浏览器查看本页面。

請滾動至頁面底部,然後使用Google Translate 改變文本的語言。如果您沒有看到Google Translate 之選項,請嘗試使用其他網頁瀏覽器查看本頁面。

Budget

~$33 Million

Through the federal government's Investing in Canada Infrastructure Program (ICIP), the Downtown Flood Barrier received funding under the Green Infrastructure stream. This is in addition to the funding from the Province of Alberta through the Alberta Community Resilience Program. Totaling 18 million for new flood protection for Downtown Calgary.

For a list of the ICIP funded projects in Alberta, see the list of Announced Federally Approved Projects.

Timeline

  • Design: COMPLETED
  • Remove trees and relocate utilities: COMPLETED
  • Hire contractor: COMPLETED
  • Mobilize to site: COMPLETE
  • Start of Construction: Summer 2021
  • Flood Wall installation: Fall 2021 – Summer 2022
  • Promenade Hardscaping and Landscaping: Spring 2022 – Fall 2023
  • Construction Completion: Fall 2023

*Construction is dependent on weather, site conditions and timing of other projects in the area. Updates will be provided regularly, but dates may change.

Found artifacts:

Past events

April 13, 2019

October 5, 2019

Stay connected

Sign up for our email updates to receive the most up-to-date information about Eau Claire Area Improvement projects.

Have questions or concerns about project construction? 

Learn more about public engagement for Eau Claire area projects.


This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null