Noise Barrier Lifecycle program
About the Noise Barrier Lifecycle Program
The City of Calgary is dedicated to ensuring the continued upkeep and safety of noise barriers through the Noise Barrier Lifecycle Replacement Program.
In the City's Noise Barrier Lifecycle Replacement Program, aging noise barrier structures are assessed through noise barrier condition inspections. The objective of these assessments is to ensure the ongoing maintenance and safety of the noise barriers. Each noise barrier within the City's road network undergoes a basic assessment annually and a detailed evaluation every five years.
The replacement of existing, aging noise barriers increase the service life of the noise barrier by approximately 50 years.
The process entails the demolition of existing posts, panels and certain piles/foundations. New piles, posts, foundation and panels are then installed.
Project update - June 2024
Work continues with the previously announced locations:
- Location 7A – Southland Dr. S.E., West of Wilde Rd. (Whitney Cr. S.E.) – South side
- Location 7B - Southland Dr. S.E. from Fairmount Dr. to 5 Street S.E. (Woodland Cr.) - South side
We can expect construction to be substantially completed by Winter 2024.
Crews have mobilized on the following locations early June 2024:
- Location 7C - Southland Dr. S.E. from Acadia Dr. to Maple Creek Dr. S.E. (Maplebrook Place S.E.)
Substantial completion of the noise barrier is expected to be completed in Winter 2024. This work will include site preparations and the demolition/removal of the existing barriers. Please see the anticipated construction impacts for more details.
Crews are expected to mobilize later this summer in:
- Location 7D (Southland Dr. S.E. from Acadia Dr. to Maple Creek Dr. S.E. – South Side) - July
- Location 1 (24 Avenue S.W. and 24 Street S.W) - August
We will post more information closer to the start date.
14 Street S.W. Noise Barrier
Construction Progress Update for Noise Barrier Replacement Project on 14 Street & 75 Avenue S.W.
![14 street noise barrier](/roads/noise-barrier-lifecycle/_jcr_content/root/maincontentpar/responsivegrid/grid/column-0-r0/grid_layout6271/column-0-r0/grid_layout_18869072/column-ae418849-6ded-4671-8b5b-d944f1131bfa0/image_2124929854_cop.img.png/1710533817752/14-street-noise-barrier.png)
March – June 2024
- Wall coating of the residential side of the wall is targeted for completion by late June, weather permitting.
- Some wall sections will remain open for a short time to help crews access and finish works on the 14 Street side. The contractor is working with Water Services to schedule the steel grade beam installation which will expand over the existing water feeder main.
- Sidewalk repairs will follow once the above work is complete.
Langriville Drive S.W. Noise Barrier
Construction Progress Update for Noise Barrier Replacement Project on Langriville Drive S.W.
![Lagriville Noise Barrier](/roads/noise-barrier-lifecycle/_jcr_content/root/maincontentpar/responsivegrid/grid/column-0-r0/grid_layout6271/column-0-r0/grid_layout/column-54fe5fd0-6d38-4160-a82c-9f6461c5a0450/image_copy.img.png/1710533801606/lagriville-noise-barrier.png)
- Crews will begin to mobilize to Langriville Drive S.W. once work is completed at 14 Street and 75 Avenue S.W.
- Additional updates and timelines will be provided as we near the construction date.
2024 Noise Barrier Replacements
Five noise barriers will be replaced throughout the Spring – Winter 2024.
Please see detailed locations and maps below:
- Southland Dr. S.E., West of Wilde Rd. (Whitney Cr. S.E.) - South side (Location 7A)
- Southland Dr. S.E. from Fairmount Dr. to 5 Street S.E. (Woodland Cr.) - South side (Location 7B)
- Southland Dr. S.E. from Acadia Dr. to Maple Creek Dr. S.E. (Maplebrook Place S.E.) – South side (Location 7C)
- Southland Dr. S.E. from 7 St. to Blackfoot Tr. S.E. (Location 7D)
- 24 Avenue S.W. and 24 Street S.W (Location 1)
Anticipated general construction impacts
- Construction work hours are Monday to Friday from 7 a.m. to 5 p.m. with construction activity on weekends only when required. Construction updates will be posted online.
- Residents will see construction activity, including construction crews, vehicles, and heavy equipment.
- Impacts may include noise, dust, and vibration due to construction activities.
- Residents may also experience increased traffic noise while the existing noise barriers are removed.
- Sidewalk closures and detours may be required but we will ensure that pedestrians and cyclists can travel safely through the area and still access their destinations.
- The temporary closure of some parking and roads may be required. Traffic will be maintained in these cases by way of local detours.
We know that construction impacts can be disruptive, and we will work to mitigate impacts as best as we can. Updates, timelines, and construction impacts will be posted on this page throughout the construction period. Thank you for your patience during this important work.
Project benefits
- We’re investing in our current infrastructure to ensure it remains in good condition for years to come.
- Lifecycle replacement involves demolition of existing posts, panels, and pile/foundations to be replaced with current standard durable materials with an expected life expectancy of approximately 50+ years.
- Improved quality of the new noise barrier compared to existing, aging noise barriers.
- The new noise barriers will have an enhanced aesthetic with low maintenance requirements.
- Calgarians living next to roads with high-volume traffic experience an improved quality of life when excessive noise volumes are reduced by a noise barrier.
Project timeline
- Spring 2024 - Construction Start
- Locations 7A and 7B – Construction began in March
- Location 7C – Construction began early June
- Location 7D – Construction is expected to start in July 2024
- Location 1 – Construction is expected to start in August 2024
- December 2024/January 2025 – Substantial completion
Construction activities are dependent on several factors. Timelines may change due to inclement weather, complexity, supply chain, and/or other unexpected circumstances.
Stay connected
Have questions? Please contact us at noisebarriers@calgary.ca or call 311.