Noise Barrier Lifecycle program
About the Noise Barrier Lifecycle Program
The construction process involves the removal of existing posts, panels and some foundations. Then, new piles, posts, foundations and panels are put in place.
Project update - December 2024
The Noise Barrier Lifecycle Replacement project team completed the replacement of seven noise barriers in 2024.
Address | Map | Status |
---|---|---|
Southland Dr. S.E., West of Wilde Rd. (Whitney Cr. S.E.) – South side |
Complete. Minor works will be finished in Spring 2025. |
|
Southland Dr. S.E. from Fairmount Dr. to 5 Street S.E. (Woodland Cr.) - South side |
Complete. Minor works will be finished in Spring 2025. |
|
Southland Dr. S.E. from Acadia Dr. to Maple Creek Dr. S.E. (Maplebrook Place S.E.) |
Complete. Minor works will be finished in Spring 2025. |
|
Southland Dr. S.E. from Acadia Dr. to Maple Creek Dr. S.E. – South side |
Complete. Landscaping and painting work will be finished in Spring 2025. |
|
Complete. Landscaping and painting work will be finished in Spring 2025. |
||
24 Avenue S.W. and 24 Street S.W |
Under design. Construction expected in 2025. |
|
Southbound Drive S.W. & 14 St. S.W.: Phase 2 – Red Wall, Eastbound |
Under design. Construction expected in 2025. |
Noise Barrier Replacement Project on 14 Street & 75 Avenue S.W.
September - December 2024
Construction to replace the noise barrier is now complete. Deficiency inspections will resume in Spring 2025. Noise Barrier Replacement Project on Langriville Drive S.W.
November - December 2024
- Construction to replace the noise barrier is now complete. Landscaping will be restored as weather conditions improve.
Project timeline
- Spring 2024 - Construction Start
- Locations 7A and 7B – Construction began in March
- Location 7C – Construction began early June
- Location 7D – Construction began July 2024
- Location 8 – Construction will began in August 2024
- December 2024/January 2025 – Substantial completion
- Location 1 – Under design. Construction is anticipated to start in 2025.
- Location 6 – Under design. Construction is anticipated to start in 2025.
Construction activities are dependent on several factors. Timelines may change due to inclement weather, complexity, supply chain and/or other unexpected circumstances.
Stay connected
Have questions? Please contact us at noisebarriers@calgary.ca or call 311.