Stoney Trail North Interchange projects

Project updates - May 19, 2020

Construction is continuing on the Stoney Trail and 14 Street N.W. interchange. Upcoming work includes installation of storm lines, formwork, rebar and concrete pours for abutments and the centre pier, and earthworks.

Design work is currently underway for improvements on two other North Stoney Trail interchanges at Shaganappi Trail and Stoney Trail N.W. and at Centre Street / Harvest Hills Boulevard and Stoney Trail N., along with a brand new interchange at 11 Street and Stoney Trail N.E.

 

About the Stoney Trail North interchange projects

North Calgary has continued to experience significant growth in population and traffic over the last few years with the existing communities north of Stoney Trail, including Nolan Hill, Sage Hill, Evanston and Sherwood Park, continuing to develop and expand. With the planned addition and development of the new communities of Carrington, Livingston, Keystone Hills and other developments in the area, further traffic stress will be added to the surrounding roadways and interchanges requiring improvements to the network in order to maintain traffic flows and support the development.

As approved in The City’s Investing in Mobility plan and the One Calgary 2019-2022 Service Plans and Budgets, The City is investing in improvements to multiple points of access along Stoney Trail. The Stoney Trail and 14 Street N.W. interchange is currently under construction with completion expected in summer 2021. This project will also include the upgrade of the existing Shaganappi Trail N.W. and Centre Street N. interchanges on Stoney Trail and the construction of a new interchange at Stoney Trail and 11 Street N.E.

  • Stoney Trail / 11 Street N.E. - new interchange
  • Stoney Trail / Centre Street N. - twinning
  • Stoney Trail / Shaganappi Trail N.W. - twinning
Edit accordion

Variables

Row Count: 4
ListCat: Stoney Trail Interchange Projects
ID: 3734

Location: Stoney Trail and 14 St NW

Description:

  • Four-lane 14 Street N.W. bridge over Stoney Trail
  • Northbound to westbound Stoney Trail and southbound to eastbound Stoney Trail 'on' ramps
  • Westbound to southbound 14 Street and eastbound to northbound 14 Street ‘off’ ramps
  • Two merge loops onto Stoney Trail
  • Tear drop traffic circles, instead of traffic signals on the north and south sides of the bridge
  • Asphalt pathways and concrete sidewalks on the east and west side of the new interchange
14 St N.W. - Stoney Trail Interchange design
 

Construction timeline: summer 2019 - summer 2021

Impacts:

  • Reduced speed limit (80 km/hr) in construction zone on Stoney Trail
  • Occasional traffic restrictions/lane closures in construction zone on Stoney Trail
  • Upcoming daytime on and off ramp closures in Spring 2020 for storm line installation. More information will be provided once dates are confirmed
  • Stoney Trail eastbound and westbound night time closures are planned in Summer 2020 for bridge girder installations. More information will be provided once dates are confirmed.

Project update: Construction activities will resume on April 20, 2020​

Edit accordion

Variables

Row Count: 4
ListCat: Stoney Trail Interchange Projects
ID: 3735

Location: Stoney Trail and 11 St NE

Description: New on-off ramps to and from the north, and a full interchange

  • Detail design is underway

Construction timeline: TBD. To be coordinated with adjacent development.

Impacts:

  • None currently
  • Site survey and preliminary geotechnical investigations are planned for May to August 2020

Project update: Detail design is currently underway​

Edit accordion

Variables

Row Count: 4
ListCat: Stoney Trail Interchange Projects
ID: 3736

Location: Stoney Trail and Centre St N

Description: Second bridge over Stoney Trail

  • Detail design is underway

Construction timeline: 2021 - 2022

Impacts:

  • None currently
  • Site survey and preliminary geotechnical investigations are planned for May to July 2020

Project update: Detail design is currently underway​

Edit accordion

Variables

Row Count: 4
ListCat: Stoney Trail Interchange Projects
ID: 3737

Location: Stoney Trail and Shaganappi Trail NW

Description: Second bridge over Stoney Trail

  • Detail design is underway

Construction timeline: 2021 - 2022

Impacts:

  • None currently
  • Site survey and preliminary geotechnical investigations are planned for May to July 2020

Project update: Detail design is currently underway​

About the Calgary Ring Road

Calgary's Ring Road is located within The Province's Transportation Utility Corridor (TUC) and is operated and maintained by the Government of Alberta through Alberta Transportation. The northwest, northeast, and southeast sections of the Ring Road (Stoney Trail) are completed and in use. Construction on the southwest and west sections are currently underway.

When the Calgary Ring Road is complete, it will provide 101 kilometers of free-flow travel around Calgary and contribute to safe and easy movement of goods and people in and around the city.

Project timelines

  • Construction start on 14 Street N.W.: summer 2019
  • Detail design of Shaganappi Trail N.W., Centre Street N. and 11 Street N.E.: 2020 - 2021
  • Construction work on Centre Street N. and Shaganappi Trail N.W.: 2021 - 2022
  • Completion of 14 Street N.W. interchange work: summer 2021
  • Construction work on 11 Street N.E.: TBD. To be coordinated with adjacent development.