Douglas Fir Trail Project

Project update – January 2026

The City has secured funding to complete detailed design work for long-term Douglas Fir Trail repair. A geotechnical consultant will be hired shortly so design work can commence.

The City always welcomes feedback and Calgarians are encouraged to sign up for the Project Newsletter to receive updates.

In the meantime, repair work on a smaller section of the slope is progressing as planned (see Figure 1 - Slope Remediation Work Area). Construction in this area is expected to be substantially completed by the end of October, 2026.

Timelines

  • Assessment study completed: October 2025
  • Repairs to a small part of the slope: September 2025 - October 2026 
  • Trail design work: 2026 
  • Looking for funding for the trail construction scope: 2026
  • Trail repair: TBC (once construction funding is secured)
  • Trail reopening: Once it is safe to do so, after repairs are completed

Contact us

Have questions or concerns about this project? Please email us at douglasfirtrail@calgary.ca.

Stay connected

Sign up to receive email updates about this project.

Related information

Figure 1 – Closure of Douglas Fir Trail and pathway area since September 2025

Why the Trail is closed

The Douglas Fir Trail is located on a very steep slope made up of loose soil and weak rock. Over many years, water, erosion, and natural wear have damaged sections of the trail and reduced slope stability, creating safety risks for public use.

In 2014, City inspections identified a small section of the slope that required major rehabilitation. This work includes addressing slope instability and replacing an aging retaining wall that supports the Bow River Regional Pathway.

In 2023, further inspections confirmed that additional sections of the Douglas Fir Trail were no longer safe to use. To protect public safety and the surrounding natural environment, the City closed part of the trail.

Later in 2023, City Council approved funding to proceed with slope stabilization repairs for the smaller, high-risk section of the slope. By fall 2025, the City had completed all required technical studies, approvals, and agreements with adjacent landowners to allow construction to move forward.

In September 2025, the trail closure was expanded to support construction activities. This includes a laydown area in the Edworthy Park parking lot and use of the Bow River Regional Pathway as an access route to the construction site (see Figure 2).

In fall 2025, a broader assessment study confirmed that some parts of the trail are in poor condition and will also require repairs. As a result, a significant portion of the trail remains closed for public safety and to accommodate ongoing slope stabilization work.

Reopening the Douglas Fir Trail depends on completing two separate but related projects:

  • Slope stabilization work, which is currently funded and expected to be completed by October 2026.
  • Larger trail repair work, which is not yet funded.

The City is seeking funding for the larger trail repair project. Once both projects are completed, The City intends to reopen the trail for public use.

Figure 2. Douglas Fir Trail closure area

We are now repairing a 150-metre section of the slope above the Bow River Regional Pathway (see Figure 1). This will help protect:

  • People using the Trail and Bow River Regional Pathway
  • The railway line below the slope
  • The long-term stability of the hillside

We ask all trail users to follow posted signs and detours during construction.

What is being repaired right now (2026)

Construction to fix the small slope instability began in September 2025 and will continue until October 2026.
Crews are:

  • Strengthening the small section of slope to help mitigate the risk to potential future movement
  • Improving drainage so help avoid washouts of the trail at that location
  • Installing slope monitoring equipment
  • Restoring the natural habitat (tree planting and landscaping) which has been damaged by washouts and users not following the marked trail

These current repairs are not focusing on rebuilding of the washed-out sections of the trail; that is The City’s next project that we spent the last 1.5 years  assessing. We are now looking for project funding to reopen the trail.

The future Douglas Fir Trail repair project

The City is developing a long-term plan to repair the Douglas Fir Trail, reduce the risk of future washouts, and reopen the trail for public use.

In January 2026, The City received funding to complete detailed design work for future Douglas Fir Trail repair options. This work may include small trail realignments to safer areas and improvements to drainage.

While slope stabilization work continues, The City will continue working with partners and the community to discuss priorities and future trail design options. These discussions will help inform the long-term repair approach.

The larger trail repair project is not yet funded, and a reopening timeline has therefore not been confirmed. The City is actively pursuing funding for this larger trail repair project. The goal is to deliver a long-term, safe, and durable solution that allows the Douglas Fir Trail to reopen in the future.

Bow River Regional Pathway Closure

A section of the Bow River Regional Pathway below the trail is closed to allow equipment and crews to safely access the slope for remediation work. We expect it to reopen in October 2026, once the repair work is complete.

Please note: this pathway closes each year approximately from November to May as part of its regular seasonal closure.

What we learned from the 2024–2025 assessment study

From January 2024 to October 2025, the City studied the full 1.5 km length of the trail to understand long-term conditions such as erosion, drainage, and stability (see Figure 1).

Key findings

  • 1,494 metres of trail were studied:
    • 991 m are in good condition
    • 228 m are in fair condition
    • 275 m are in poor condition
  • Several areas show constant washout.
  • Some older trail sections and structures do not meet City’s current structural, durability, and/or accessibility standards.

Future work to reopen the trail will need to:

  • Potentially realign 2 small portions of the trail to the lower part of the slope, moving them to a safer area to help avoid the constant washouts.
  • Improve drainage and reduce future erosion.
  • Protect plants, wildlife, and the natural look of the trail.
  • Renaturalize portions of the trail damaged by users not staying on the marked trail itself.
  • Planting new trees and landscaping.

Douglas Fir Trail project background

Slope instability and erosion have affected the Douglas Fir Trail since it was built in the 1960s. Over the years, several studies and repairs have taken place, including volunteer work. However, volunteer repairs are no longer recommended because previous improvements only lasted a few years before eroding again.

Key historical milestones:

none

Category Icon and Label

1960s The trail was built.

Start Date | End Date

none

Category Icon and Label

1970s The first signs of slope instability were found.

Start Date | End Date

none

Category Icon and Label

2005 More instability was found on the upper slope, and a retaining wall and drainage system were installed.

Start Date | End Date

none

Category Icon and Label

2009 A small section of the slope failed, but it was stable enough to be monitored only.

Start Date | End Date

none

Category Icon and Label

2013 Flood caused erosion near the railway embankment, and CPKCR built a protective structure to stabilize the slope.

Start Date | End Date

none

Category Icon and Label

2014 New slope instability was identified at the area we are out repairing today. Regular monitoring of the area has happened by The City since then.

Start Date | End Date

none

Category Icon and Label

2016-2017 Volunteers completed trail repairs, but the trail remained stable for only about five years.

Start Date | End Date

none

Category Icon and Label

2019 A conceptual design report was completed for future improvements.

Start Date | End Date

none

Category Icon and Label

2023 Council approved funding for our current small slope instability remediation project. Detailed design and interested party negotiations commenced.

Start Date | End Date

none

Category Icon and Label

2023 The City closed part of the trail in November 2023 because it was deemed unsafe for the public (see adjacent photo of existing trail conditions).

Start Date | End Date

none

Category Icon and Label

2025 Temporary closure in September 2025 of a wider portion of the trail network was undertaken to allow construction of our small slope instability remediation project (to ensure the public doesn’t accidentally wander into our construction site). Includes laydown area for our project in a portion of Edworthy Park’s parking lot and closure of regional pathway as access route to site.

Start Date | End Date

none

Category Icon and Label

2024-2025 The City completed a full assessment of the entire trail to determine funding requirements to create a durable long-lasting trail solution for the trail to help avoid the regularly occurring washouts and closures.

Start Date | End Date

none

Category Icon and Label

In 2026 Complete a detailed design. Seek funding as part of the next budget cycle to reopen the poor sections of the trail.

Start Date | End Date

none

Category Icon and Label

2026-2027 If funding becomes available: complete design work (potential small trail realignments to safer zones and channelization of drainage issues), hold public information sessions, consult with adjacent landowners, obtain regulatory approvals, and complete environmental baseline studies.

Start Date | End Date

none

Category Icon and Label

Douglas Fir Trail reopening – TBD City’s goal is to provide a long-term, safe, durable solution to reopen the Douglas Fir Trail. The City continues monthly slope monitoring of the slope to guide project decisions.

Start Date | End Date

Frequently asked questions

Is there any risk to nearby homes?

The City is conducting monthly inspections to help monitor the Douglas Fir Trail slope. At this time, based on our data, there is no immediate danger to the adjacent properties.

Is the Bow River pathway closed?

Yes. The Bow River Pathway closes every winter from November to May. It is also closed in this area until October 2026 to facilitate slope repairs. When complete, the Bow River Pathway will continue to be closed seasonally every winter from approximately November to May due to unsafe icy conditions. 

When will the Douglas Fir Trail reopen?

The project to repair the poor condition of the trail is not funded yet, so the reopening date is unknown. One option being considered is realigning 2 small portions of the trail to the lower part of the slope, moving them to a safer area to help avoid the constant washouts; improving drainage to reduce future erosion.

In 2026, we will actively look for funding to repair the trail. Currently we've received funding for a detailed design. Future construction on the trail would also need to meet regulatory requirements such as Water Act approval, biophysical and historical resource assessments, environmental baseline studies, and coordination with Canadian Pacific Kansas City (CPKC) Railway. We will continue to explore funding opportunities to support future trail development and repairs.

Can I volunteer to help with trail restoration?

We appreciate the community’s interest in volunteering, but for safety reasons, volunteer work is not possible at this time. 

Why is the City doing construction in Douglas Fir Trail now?

Construction is underway because 2023 geotechnical inspections identified instability along a 150-metre section of the slope that poses a safety risk. After completing required approvals with adjacent landowners, construction began in September 2025 and is expected to finish in October 2026. The larger section of the trail will remain closed until funding is secured for additional trail repairs.

Is the City removing the trail or replacing it with a paved pathway?

No. The City does not intend to permanently remove the trail and, will not replace the trail with a paved pathway. We are exploring moving parts of the trail that are in poor condition to a safer part of the slope.

How is the Douglas Fir Trail closure related to the habitat restoration project?

The City is working on a 10-year plan to improve Edworthy Park’s habitat and protect its wildlife while making sure the park is still accessible to the public. Ongoing restoration projects in the park are happening alongside efforts to reopen the trail.

What were the results of the recent geotechnical assessment study (2024-2025)?

The 2024-2025 study found water seepage, erosion, and worn-out areas. Of the 1,494 metres reviewed, 991 metres are good, 228 metres are fair, and 275 metres are poor. Future work should avoid unstable areas and protect the environment. No instability was noticed in the studied portion of the trail.

When did the south parking lot close to the public, and how long will it remain closed?

The gravel part of the south parking lot will be temporarily closed for staging and equipment storage during the construction starting from September 2025. This closure is expected to last until late fall 2026. Also, part of the Bow River regional pathway will need to close temporarily during construction for access. Signs will be posted in advance to notify park users.

Are there alternative parking options?

Yes. While the south gravel parking lot will stay partly open during construction, visitors can also use the north parking lot, which connects to Edworthy Park.

Can people still use the park space and trails on the south side?

The paved part of the south parking lot is open during construction, but the gravel part of the parking lot is being used for construction staging.


This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​