Altadore-North Glenmore area construction
Stay connected
Sign up for our email updates to receive the most up-to-date information about the Altadore-North Glenmore construction projects.
Contact us
Have questions or concerns? Email our project team at: AltadoreGlenmoreArea@calgary.ca
About the projects
The City of Calgary is investing in public spaces, recreation and roadway infrastructure in the Altadore-North Glenmore area, with construction of several significant projects kicking off in 2025.
These projects will deliver new twin-arena and track and field facilities at Glenmore Athletic Park, upgrade the 50 Avenue S.W. roadway from Crowchild Trail S.W. all the way into Sandy Beach Park (including parking lots), new multiuse pathways, resurface Glenmore Trail S.W. from Crowchild Trail S.W. to Elbow Drive S.W. and replace the noise barrier along Crowchild Trail from Glenmore Trail S.W. to 50 Ave S.W.
City teams are working collaboratively to coordinate projects to help mitigate impacts and provide community members with up-to-date information on timelines, detours and milestones.
Active projects in Altadore-North Glenmore
Construction impacts and detours
Details and schedules subject to change
Location | Construction Details | Anticipated Schedule | More information |
---|---|---|---|
50 Avenue S.W. | Road resurfacing and multiuse pathway extension | Rescheduled to Spring 2026 – Fall 2026 | Work has been rescheduled to spring 2026 to complete construction in one season. |
Glenmore Trail S.W.: Lake View Golf Course Section | Noise barrier replacement | Spring 2025 – Winter 2025 | Construction of the noise barrier is currently underway. |
Crowchild Trail S.W. - East side (53 Ave. S.W. to 50 Ave. S.W.) | Noise barrier replacement | Spring 2025 – Winter 2025 | Construction of the noise barrier at this location is currently in the procurement phase. A timeline will be established once a contractor is on board. The project team will notify residents in the area in advance of the construction start date. |
Glenmore Trail S.W. repaving (Crowchild Trail to 14 St) | Milling and paving | July 2025-October 2025 | Construction will be completed during off-peak daytime and overnight. Milling and base layer paving is complete. Concrete rehabilitation is underway, followed by final paving and lane painting. |
Sandy Beach Park improvements | Road paving (complete), regional pathway realignment, pathway construction and landscaping | Summer to Fall 2025 | Construction is underway on the pathway realignment and landscaping. |
Glenmore Twin Arena | Construction | Spring 2025 to late 2027 | Excavation work is complete and construction is underway on the facility’s substructure and interior structure. |
Projects map
Projects displayed on the map are subject to change in scope.