Bridge rehabilitation: Flood mitigation repairs

The City has completed flood mitigation work on three bridges situated along Nose Creek, that were in need of important repair work to ensure the deteriorated flood mitigation elements are safe and in good working condition.

Project update - Fall 2025

This project is now substantially complete.

Expansion joint at the Goddard Avenue and Beaverdam Road bridges has been completed, pathway improvements have also been made to improve connectivity along the Nose Creek Pathway and site restoration was completed in Summer and Fall 2025.

Please Note: Some additional work on the Goddard Avenue bridge is now expected to be completed in 2026. The flood mitigation repairs are complete, however there was damage sustained underneath the bridge in Spring 2025 from the fire of an encampment, The City will need to repair those damages next year.

Project timelines

  • August 2024 - Construction started
  • December 2024 - Construction on 41 Avenue substantially complete
  • Summer 2025 - Construction on Goddard Avenue and Beaverdam Road substantially complete

Bridge locations

The following bridges have been undergoing repairs:

41 Avenue over Nose Creek Bridge – Work Completed

Project scope of work

The physical condition of various elements of this bridge had declined to the point where work was needed to keep the bridge in service. The project rehabilitated the deteriorated bridge and flood mitigation elements and will extend the service life of the bridge by approximately 30 years.

The scope of work included:

  • Traffic barrier replacement
  • Girders and deck repair
  • Substructure repair
  • Expansion joints modifications
  • A new multi-use pathway on the south side
  • Replacement of damaged slope protection
  • Improvements to the 41 Avenue and Edmonton Trail intersection
  • Adding a missing pathway on the north side of 32 Avenue

*NEW * adding a missing pathway on the north side of 32 Avenue NE

The new multi-use pathway at the 41 Avenue bridge
The new multi-use pathway at the 41 Avenue bridge
Completed work on 41 Avenue bridge
Completed work on 41 Avenue bridge

Goddard Avenue and Beaverdam Road Bridges

Project scope of work

  • Replacement of damaged slope protection
  • Concrete barriers repair
  • Girders and substructure repair
  • Expansion joints replacement
Slope protection work currently underway on the Beaverdam Road Bridge
Slope protection work currently underway on the Beaverdam Road Bridge

Environmental considerations

  • An Environmental Impact Assessment was conducted and mitigation measures were in place throughout construction.
  • Efforts were made to minimize environmental impacts during the execution of the projects.
  • Necessary Environmental and other Regulatory Permits are approved and in place.

Benefits

  • Improve the condition, appearance, and safety of the bridges.
  • Improve safety for pedestrians and improve pedestrian connectivity, and
  • Extend the service life of the bridges for many years to come.

Budget

The estimated investment for this project is $3.3 million.


This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null