Memorial Dr. E and 36 St S.E. Paving
Project update - August 2025
Construction begins in the first week of September 2025.
What's happening and when
September 2025
- Construction of multi-use pathway on both sides of 36 Street S.E.
- Construction of multi-use pathway along the north side of Memorial Drive E.
- Various concrete repairs and utility work on 36 Street S.E.
October 2025
- Continue work on pathways, removing and replacing curbs
- Pavement mill/inlay on 36 Street S.E.
- Temporary road widening of Memorial Drive E.
November 2025
- Clean up and construction completion for 2025
2026
- Detailed scheduled to be provided early in 2026
Please note: construction schedules may change due to weather or other issues.
Traffic and community impacts
We know construction can be inconvenient. We are doing our best to reduce the impact on your community.
- Lane closures: At least one lane will stay open. Watch for road signs.
- Lane closures will happen during the day. We will let you know ahead of time.
- Pathway and concrete work: 9 a.m. to 3 p.m., weekdays
- Pathway and concrete work: 7 a.m. to 8 p.m., weekends
- Paving: 7 a.m. to 8 p.m. on weekends
- Work hours: For all construction activities, working hours will generally be from 7 a.m. to 6 p.m. on weekdays and from 7 a.m. to 8 p.m. on weekends
- Noise and vibrations: You may hear or feel construction, but we’ll try to keep it minimal.
About the project
As part of a continuing program of major road restoration, The City is planning to complete pavement rehabilitation and road reconstruction on Memorial Drive E. from 36 Street S.E. to Marlborough Way/ 39 Street and 36 Street S.E. from Memorial Drive E. to 8 Avenue S.E. Multiple sections of the roadway show excessive distress, various cracking patterns and severity that have affected pavement performance.
This project will improve roadway operation, surface characteristics, and help to ensure the road continues to be safe, functional and in great condition for years to come. These upgrades will bring the road up to modern standards, improve traffic flow, enhance safety and pavement performance while improving connections for pedestrians and cyclists.
Budget
The construction budget for this project is $6 million.
Project details
The project will include:
- Full pavement reconstruction for Memorial Drive E. westbound lanes
- Mill and Inlay (120mm) for Memorial Drive E. eastbound lanes
- Mill and Inlay (100mm) for 36 Street S.E. roadway
- Removal and replacement of damaged curbs, sidewalks, medians and islands, and wheelchair ramps
- Various safety improvements on Memorial Drive and traffic signal relocations at the Memorial Drive E./ 39 Street S.E. and 36 Street S.E./ Radcliffe Drive intersections
- Construction at multiple locations of new walking and wheeling connections or connections to the existing network
- Replacement of any catch basins that are damaged or in poor condition
As part of a continuing program of major road restoration, The City is planning to complete pavement rehabilitation and road reconstruction on Memorial Dr. E from 36 St. SE to Marlborough Way/39 St. and 36 St. SE from Memorial Dr. E to 8 Ave. SE. Multiple sections of the roadway show excessive distress, various cracking patterns and severity that have affected pavement performance.
More information
- Visit calgary.ca/trafficinfo for real-time updates on road closures and traffic changes.
- Tune in to 107.9 FM for live traffic info.
- Roadway Activities Map