Anderson Road S.E. Paving
Project update – May 2026
Construction on Anderson Rd. S.E. has resumed after the winter break. Work is taking place between Macleod Trail S. and the Deerfoot Trail S.E. boundary.
Our contractor, PME Inc., returned in late April 2026. Crews began by removing temporary concrete barriers in the westbound lanes between Deerfoot Trail and Acadia Dr., and refreshing road markings.
Next, crews will complete concrete repairs and mill selected areas of the road. After that, paving crews will place the final layer of asphalt. New overhead signs will be installed in the fall. Landscaping work will be completed later to finish the project.
The Anderson Road S.E. paving project includes fixing the road surface, as well as replacing sidewalks and wheelchair ramps. These improvements will make the area safer and easier to use for people walking, biking, or using mobility aids.
What's happening and when
Spring-summer 2026
- Removal of temporary concrete barriers on Anderson Road S.E. westbound between Deerfoot Tr and Acadia Dr S.E.
- Completion concrete repairs
- Completion of milling
- Completion of top lift of asphalt paving
- Installation of new overhead signs
The work is anticipated to be completed in fall 2026.
Please note: construction schedules may change due to weather or other issues.
Timeline of past work in 2025
April 2025
- Removing and replacing curbs
May 2025
- Continue removing and replacing curbs
- Intersection upgrades at Acadia Drive S.E.
June 2025
- Complete curb replacement
- Start building the new third eastbound lane
- Complete intersection upgrades at Acadia Drive S.E.
- Begin milling and repaving the old lanes
- Intersection upgrades at Bonaventure Drive S.E.
July 2025
- Continue building the new third eastbound lane
- Continue milling and repaving the old lanes
- Continue intersection upgrades at Bonaventure Drive S.E.
- Complete sidewalks and wheelchair ramps
August 2025
- Complete curb replacement
September 2025
- Complete Anderson Road old pavement milling
- Begin Anderson Road asphalt base lift
- Start widening (adding the third lane) of Anderson Road eastbound between Bonaventure Drive and Deerfoot Trail
- Milling and paving of Acadia Drive
- Begin 200 m of full road reconstruction – outside lane of Anderson Road eastbound, east of Acadia Drive
October 2025
- Complete Anderson Road asphalt base lift
- Continue widening (adding the third lane) of Anderson Road eastbound between Bonaventure Drive and Deerfoot Trail
- Complete dual left turn from Anderson Road eastbound to Bonaventure Drive northbound
- Complete 200 m of full roadway reconstruction outside lane of Anderson Road eastbound, east of Acadia Drive
November 2025
- Complete widening (adding the third lane) of Anderson Road eastbound between Bonaventure Drive and Deerfoot Trail and open to traffic
December 2025
- Reinstall high tension cables in the median between Deerfoot Trail and Acadia Drive
Spring 2026
- Remove temporary concrete barriers on Anderson Road westbound between Deerfoot Tr and Acadia Drive
- Complete top lift of asphalt paving
- Install new overhead signs
Please note: construction schedules may change due to weather or other issues.
Traffic and community impacts
We know construction can be inconvenient. We are doing our best to reduce the impact on your community.
- Lane closures: At least one or two lanes will stay open. Watch for road signs.
- Lane closures will happen during the day and at night. We will let you know ahead of time.
- Work hours:
- Concrete work: 9 a.m. to 3 p.m., weekdays and weekends
- Paving: 9 p.m. to 5 a.m. on weekdays; 9 p.m. to 8 a.m. on weekends
- Noise and vibrations: You may hear or feel construction, but we’ll try to keep it minimal.
- Transit: Transit along Anderson Rd S.E. may be impacted by ramp closures. Check calgarytransit.com for updates.
About the project
This work is part of Calgary’s 2026 Annual Paving Program and includes improvements along Anderson Rd S.E., from Deerfoot Trail to Macleod Trail.
The construction budget for Anderson Road S.E. paving project is $7.7 million.
We are:
- Adding a third eastbound lane
- Repaving the road
- Fixing sidewalks, curbs, and wheelchair ramps
- Updating traffic lights at Bonaventure and Acadia Drive
- Putting up new overhead signs
These upgrades will make the road last longer, improve safety, and make it easier for everyone to get around.