Outfall repair program

About the projects
Project Updates
Mid-August 2021 – April 2022
River access and pathway detours
Starting mid-August we will be repairing outfalls E63 and E64 located on the west bank of the Elbow River, adjacent to the Glenmore Water Treatment Plant and across from the Calgary Golf and Country Club.
August – October 2021 – the east pathway around the Glenmore Water Treatment Plant will be closed. The detour will be via the west pathway.
August – April 2022 – There will be no access to the Elbow River between the Glenmore Reservoir and downstream of the construction area. Signage will direct users to Sandy Beach.
View the information notice for more information.
As a part of our flood recovery work, we are repairing the following outfalls:
Completed in 2018
- B32
- B34
- B36
- B68
- B69
- B74
- B75
- B77/78
- B79
Completed in 2019
- E38
- E40
- E43
- E54
- E63/E64
- N10
- N31
- N41
Completed in 2020
- B119
- E40
In progress
- B75 - estimated completion October 2022
- IC9A - estimated completion November 2022