Last updated: January 15, 2024
To make way for the Green Line stations and tunnel under 2 Street S.W., work is underway to move underground utilities (e.g., Telus, ENMAX) away from 2 Street and into adjacent streets and avenues.
Location | Project type | Impact | Status | End date | Details |
---|---|---|---|---|---|
6 Avenue S.W. between 1 and 2 Street S.W. |
ENMAX utility relocation |
|
Active |
February 2024 |
|
6 Avenue, 2 Street S.W., 3 Street S.W. | Bell/Zayo Utility Relocation |
|
Active | Late February 2024 | |
5 Avenue at either side of 2 Street S.W. |
ENMAX utility relocation |
|
Active |
April 2024 |
|
3 Avenue west of 2 Street S.W. |
City of Calgary Water Infrastructure Relocation |
|
Upcoming |
Early March |
|
2 Avenue between 2 and 3 Street S.W. |
ENMAX Utility Relocation |
|
Active
|
End of April 2024 |
To make way for the Green Line station and tunnel under 11 Avenue S.E., we are moving underground utilities (storm water and sanitary) into 12 Avenue S.E.
Location | Project type | Impact | Status | End date | Details |
---|---|---|---|---|---|
3 Street S.E. between 10 and 11 Avenue |
ENMAX Utility Transmission |
|
Active |
Late February 2024 |
|
6 Street S.E. between 11 and 12 Avenues |
City of Calgary Utility Relocation |
|
Active |
End of March 2024 |
To make way for the Green Line station and tunnel under 11 Avenue S.W., we are relocating and realigning existing third-party utilities away from 11 Avenue S.W. into adjacent streets, avenues and alleyways.
Location | Project type | Impact | Status | End date | Details |
---|---|---|---|---|---|
Centre Street, 11 Avenue, 12 Avenue |
ATCO Utility Abandonment and Capping |
|
Active |
February 2024 |
Work is planned for this area to make way for the future Ogden station.
Location | Project type | Impact | Status | End date | Details |
---|---|---|---|---|---|
78 Avenue S.E. |
Secant pile wall |
|
Active | End of year 2024 | |
78 Avenue S.E. Near 72 Avenue S.E. 69 Avenue. S.E |
78 Avenue S.E. vehicle tunnel and a pedestrian tunnel near 72 Avenue S.E. |
|
Active | Estimated to be completed by summer 2025 |
See the 78 Avenue Project page |