Riley Area construction projects

The City of Calgary is investing in our infrastructure and public spaces to provide meaningful improvements for Riley area residents and businesses.

This coming spring and summer numerous projects will begin in the Riley area. These projects deliver a vision for the area that combines flood mitigation with vibrant public spaces and upgrades to community infrastructure.

The City is working collaboratively across project teams to provide up-to-date information with community members and help mitigate impacts on those in the area. 

Stay connected

Sign up for email updates to receive information about Riley Area projects and events. 

Have questions or concerns?

Related links

Where is construction happening?

View details on the construction impacts for the Riley Area below*.

Sunnyside

Sunnyside

Location Closure Details Anticipated Schedule More Information Project

2 Ave & 7 Ave N.W. between 10 St N.W. to 4 St N.W.  

  • Second phase: along south side of 2 Ave N.W. between 8 St to 5A St N.W.

Single lane closure.

Two-way traffic will be maintained with no parking on the north side of the street during construction work hours.   

April 22 - Fall 2025

  • Work will be kept to one side, covering two blocks at a time, before moving to the other side of the road.
  • Parking restricted adjacent to work areas.

Mobility Improvements: 2/7 Avenue

4 Ave N.W. at 8 St N.W. to 9A St N.W. Road and intersection closure May 31 - June 14   - Closures will only occur on weekend date, when necessary There will be no parking at 4 Ave N.W. at 8 St N.W. to 9A St N.W. Follow detour and closure signage in the area  Sunnyside LRT Crossing Arm Upgrades

4 Ave N.W. between 7 St and 10 St N.W.

Closed while crews complete top lift asphalt. 

June 9 – 15

Avenue will be paved in two sections:

  • 7 St N.W. to the east side of the train tracks.
  • 10 St N.W. to the west side of the train tracks.

There will be no street parking during this time.

Pedestrian access will be maintained on both sides of the street.

Local access to parking lots will be maintained between 9A St and 10 St N.W.

Gladstone connect

7 St N.W. to Prince’s Island Park Pedestrian Bridge

Pedestrian traffic will be detoured to the sidewalk on the north side of Memorial Drive N.W.  

April – October

Full closure of the pedestrian pathway.

Sunnyside flood barrier

McHugh Bluff pathway between 5A St. and 6 St. N.W.

Pathway closure.

Ongoing to Summer 2025

Pathway users to follow the detour routes indicated by signage at the pathway entrances.

McHugh Bluff Slope Remediation

Memorial Drive Eastbound between 10 St and Centre St N.W.

Eastbound lanes will be closed, all eastbound traffic will be detoured to one westbound lane.

April – October 2025
  • One westbound lane and one eastbound lane will remain open per direction. Expect delays. 
  • Signal timing has been adjusted to optimize traffic flow.

Sunnyside flood barrier

Peace Bridge to 7 St N.W.
  • Pedestrian traffic will be detoured to the sidewalk on the north side of Memorial Drive N.W.
  • Access to the Peace Bridge will remain open throughout construction via 9 St N.W. or 7 St N.W.  
May – September

Full closure of the pedestrian pathway.

Sunnyside flood barrier

Sunnyside LRT Station

CTrains will use one platform for both directions of travel.

May 31- June 14  - Closures will only occur on weekend date, when necessary

One platform will be accessible and operational. 

Pedestrian access will be limited at all crossings. 

Emergency access will remain available. 

Road closures may be needed to support this work, please follow signage and detour information in the area.

Sunnyside LRT Crossing Arm Upgrades

*Anticipated schedule and duration of work is subject to change depending on factors such as complexity, weather, supply chain, and access

Hillhurst

Hillhurst

Location Closure Details Anticipated Schedule More Information Project

10 St N.W. between the pathway just north of 5 Ave N.W. and the end of the C-Train Bridge.

Single northbound daily lane closure from 9 a.m. – 3 p.m.

Sidewalk and cycle track closed 24/7. 

Ongoing- Summer 2025

  • Northbound vehicle traffic will be detoured into the centre northbound lane.
  • Pedestrians will be detoured at 5 Ave and 13 Ave N.W. to the sidewalk on the west side of 10 St N.W.
  • Cyclists will use the temporary Bike lane set-up next to the northbound lane closure. 

Upper Plateau Separation 

14 St N.W. to Poppy Plaza

Wheeling traffic will be detoured to the south (downtown) Bow River Pathway.

July – October

Full closure of the wheeling pathway.

Sunnyside flood barrier

*Anticipated schedule and duration of work is subject to change depending on factors such as complexity, weather, supply chain, and access

Construction impacts:

Impacts may differ by project. Please visit the project webpage for details.

Project map

Click to enlarge image.

Projects displayed on the map are subject to change in scope.

Do you want to receive construction updates right to your inbox?

Navigating Calgary traffic and detours

The City has partnered with Waze to help Calgarians navigate construction detours and closures.  

Traffic information map

View the interactive map to see road closures and construction projects occurring across Calgary.

Riley Area construction events

The City is working closely with the community to keep residents and business owners informed about upcoming work in the area.

You can find information on our upcoming events and view recordings of previous virtual events below.

Upcoming events

At this time we do not have any upcoming events scheduled. 

Previous events

Spring 2025 Update to the Community

Watch a recording of our Spring 2025 Update to the Community.

Recorded live on March 11, 2025.

2024 Fall Update

Watch a recording of our 2024 Fall Update to hear from the project teams and learn more about construction progress and schedules.

Recorded live on October 16, 2024.

2024 Spring Update

Virtual information session: Construction projects coming to the Riley Area

Watch a recording of our virtual live event to see what changes are coming, where impacts will occur and what we are doing to help businesses and residents prepare.

Recorded live on April 16, 2024.


Your personal information is collected pursuant to Section 33(c) of the Freedom of Information and Protection of Privacy (FOIP) Act. Your personal information may be used and disclosed for the purpose of event registration and your participation in Riley Area information sharing. Personal information is collected via Eventbrite and disclosed to The City of Calgary (“The City”). For information on Eventbrite’s personal information please visit their website. If you have any questions about this collection, use, and or disclosure of personal information please contact the Community and Business Relations Strategist for the area at Capital Priorities and Investment, Floor 2, Water Centre, 625 25 Ave SE, Calgary, AB, T2P 2M5, or call 403-818-4539.

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null