12 Avenue South Improvements

12 Avenue S.W. - Phase 3 Improvements

Project update

Technical work on the Phase 3 design is now wrapping up and we will soon share the final design with the community. Construction is anticipated in 2021.

Project overview

In recent years, The City has been making improvements along the 12 Avenue S.W. corridor. Work completed to date includes upgraded driving lanes between 4 Street and 11 Street S.W. and a western extension of the cycle track between 11 Street to 15 Street S.W. 

Construction on the third and final phase was initially planned for 2020. The design presented to the community in 2019 required the removal of a significant amount of on-street parking, which was not ideal. We decided to pause our 2020 construction plans so the project team could refine the design to preserve some of the on-street parking along 12 Avenue S.W. while keeping the intent of the project and providing more travel options. The technical work is now wrapping up and we will share the revised final design with the community later this year.

Improvements planned for 2021 include:

  • Extending the two-way cycle track facility on the north side of 12 Avenue S.W. from 15 Street to 19 Street S.W., and then on the east side of 19 Street S.W. from 12 Avenue to 10 Avenue S.W.
  • Providing a dedicated cycling facility for all ages and abilities, separated from vehicular traffic by parking curbs and/or flexible delineators.
  • Using the on-street cycle track to physically narrow the roadway, reducing vehicle speeds and improving safety of pedestrians/cyclists.
  • Retaining one vehicle lane on 12 Avenue S.W. between 15 Street and 19 Street S.W. to preserve some of the on-street parking on 12 Avenue S.W.
  • Retaining one south-bound vehicle lane is retained on 19 Street S.W., from 10 Avenue to 12 Avenue S.W., with parking consolidated to the west side of 19 Street S.W.
  • Improving sidewalk ramps at most intersections to line up with pathway routes crossing the street.
  • Removing two right hand turning lanes at 10 Avenue and 19 Street S.W. and at 12 Avenue and 18 Street S.W. to reduce turning speeds, shorten pedestrian crossing distances and improve sightlines.
  • Adding a new traffic signal at 10 Avenue and 19 Street S.W. to facilitate crossings on 10 Avenue S.W.
  • Add a connection for pedestrians and cyclists to the Bow River Pathway.

Here is a map of what you can expect for Phase 3 in 2021: 16 Street S.W. to 19 Street. S.W. then across 10 Avenue S.W. to the Bow River Pathway (revised design to be finalized in 2020)

Additionally, surface overlay repaving along 19 Street S.W. is planned for 2021.

Learn more about the types of cycle tracks and bike lanes and tips for cycling in Calgary.

For tips on snow-clearing a sidewalk beside a cycle track, please review this information and share with contractors.

Fast Facts:

  • 12 Avenue is one of the top five busiest bikeways in Calgary.
  • Since 2015, over 890,000 bicycle trips have been made on 12 Avenue near the 8 Street S.W. count station.

Frequently Asked Questions

Construction

When does construction start?

Construction is anticipated in 2021. Prior to construction, we will provide project updates via email and on this page.

Will access to 12 Avenue S.W. be closed at any time during construction?

12 Avenue South will remain open for the duration of the project. We will make every effort to minimize impacts during construction and will notify impacted residents prior to any disruptions due to construction.

Why didn’t construction happen in 2020?

Construction on 12 Avenue S.W. was originally planned for 2020. The initial design included the removal of a significant amount of street parking between 15 Street and 19 Street S.W., which was not ideal. We decided to take extra time to make revisions that preserve some of the on-street parking while keeping the intent of the project and providing more travel options along the corridor. As this technical work takes time, and construction is weather-dependent, it was not feasible to complete the work before the end of the 2020 construction season.

Is this project related to construction completed along 12 Avenue S.W. in 2019?

Work on Phase 1 and Phase 2 was completed in October 2019. Several improvements made along the corridor included:

  • Extending the dedicated lane for people cycling from 11 Street to 15 Street S.W.
  • Adding bicycle turn boxes at 12 Avenue and 11 Street S.W.
  • Improving travel time for drivers by providing three uninterrupted driving lanes for morning rush hour.
  • Removing the rush hour parking restriction on the north side of 12 Avenue between 15 Street and 16 Street S.W.
  • Providing a loading stall on the east side of 12 Street S.W., just north of 12 Avenue S.W.

Check out the maps for the improvements we completed in Phases 1 and 2:

Parking

How will parking and loading change on the corridor?

To allow for smooth and predictable traffic flow, on-street parking on the south side of the roadway will remain. Some of the on-street parking on the north side will also remain, however, short sections will remain as Loading Zones to ensure emergency services can continue to have access to both sides of the street. 

Engagement

What engagement was done for 12 Avenue S.W. improvements?

Public engagement for 12 Avenue S.W. improvements was conducted in 2019. Read the What We Heard report to learn more.

Initial Phase 3 designs were presented to the community in late 2019. As a result of continued community concern regarding the availability of on-street parking, we did more technical work on the design in 2020. The revised final design is now being completed and construction is anticipated in 2021.

Cycle track network

Why was 12 Avenue South chosen as a cycle track corridor?

A number of corridors, or groupings of streets, were identified for the Centre City study area based on the idea that a single cycle track within the corridor would be able to appropriately serve the demand for that specific area. For each corridor, a number of potential cycle track alignments were identified.

These alignments were based on current best practices in North American bicycle planning and design, understanding of the local context, and feedback received during the ongoing engagement. These cycle track alignments (combining a street selection and facility layout) were then evaluated based on a set of technical criteria including connections to key destinations, existing and future bicycle demand, impact on other modes, conflicts at driveways and transit stops, and cost and constructability. Based on this analysis, 12 Avenue was selected to serve the demand for an east/west corridor in the north part of the Beltline. Additional background information can be found in the Centre City Cycle Track Network- Development and recommendations report.

Future extensions

What about a cycle track extension on the east end (Olympic Way S.E. to the Elbow River)?

We have started planning for the east extension, from Olympic Way S.E. to the Elbow River pathway, and are working with CMLC and stakeholders to determine opportunities for construction, given the close proximity to the new Calgary Event Centre. More information will be available in 2021.

Stay connected

Sign up for 12 Avenue S.W. updates

Questions?

Contact 311.


Engagement

Public engagement was conducted in Spring 2019. In total, we talked to 260 people and over 60 businesses through the open house events, door knocking sessions and online. Thank you to all who provided input. Information from the previous engagement session is available.