2026 Partnering with Industry Showcase

2026 Partnering with Industry Showcase

On Thursday, January 22, 2026 the annual Partnering with Industry Showcase (PWIS) was-hosted by the Alberta Roadbuilders and Heavy Construction Association and Calgary Construction Association.

This event brought together City staff, public partners and local industry to share ideas and build relationships. 

Event highlights

2026 Upcoming capital investments and procurement opportunities

Procurement opportunities are organized according to the market timeline, beginning in Q1 2026.

Project Development

Utilities project development

Project   Market timeline  Contract value  Estimated project value  Type 
Project   : Water Distribution Flow Monitoring Equipment  Market timeline  : Q1 2026  Contract value  : <$1M    Estimated project value  : <$10M  Type  : Goods 
Project   : Bonnybrook Wastewater Treatment Plant Fermenter Upgrades  Market timeline  : Q1 2026  Contract value  : <$1M  Estimated project value  : $50M - $100M  Type  : Consulting 
Project   : Bonnybrook Wastewater Treatment Plant Headworks Expansion  Market timeline  : Q1 2026  Contract value  : <$1M  Estimated project value  : $100M - $150M  Type  : Consulting 
Project   : 15 St Sanitary Siphon Planning    Market timeline  : Q1 2026  Contract value  : <$1M  Estimated project value  : $10M - $50M  Type  : Consulting 
Project   : Water Distribution Booster Chlorination Strategy  Market timeline  : Q2 2026  Contract value  : <$1M  Estimated project value  : N/A  Type  : Consulting 
Project   : Glenmore Water Treatment Plant Boiler Replacement Conceptual Design  Market timeline  : Q2 2026  Contract value  : <$1M  Estimated project value  : <$10M  Type  : Consulting 
Project   : Potable Water Energy Recovery Facilities Conceptual Design  Market timeline  : Q3 2026  Contract value  : <$1M  Estimated project value  : <$10M  Type  : Consulting 
Project   : Bonnybrook Wastewater Treatment Plant Solids Upgrade / Expansion  Market timeline  : Q3 2026  Contract value  : <$1M  Estimated project value  : $250M - $300M  Type  : Consulting 
Project   : Confederation Park Community Drainage Improvement – Concept Design  Market timeline  : Q4 2026  Contract value  : <$1M  Estimated project value  : $10M - $50M  Type  : Consulting 

Facilities and places

Project   Market timeline  Contract value  Estimated project value  Type 
Project   : Yorkville Fire Station  Market timeline  : Q1 2026  Contract value  : $1M - $5M  Estimated project value  : $20M - $30M  Type  : Consulting 
Project   : Greyhound Building Future Use  Market timeline  : Q1 2026  Contract value  : $1M - $2M  Estimated project value  : $5M - $10M  Type  : Consulting 
Project   : South Central Bus Maintenance and Storage Facility & Victoria Park Transit Facility Decommissioning  Market timeline  : Q2 2026  Contract value  : >$50M  Estimated project value  : >$500M  Type  : Consulting 
Project   : Shaganappi Clubhouse Redevelopment  Market timeline  : Q2 2026  Contract value  : $1M - $5M  Estimated project value  : $30M - $40M  Type  : Consulting 
Project   : Tomkins Park Washroom Replacement  Market timeline  : Q2 2026  Contract value  : <$1M  Estimated project value  : $1M - $2M  Type  : Consulting 
Project   : Southland Leisure Centre Modernization  Market timeline  : Q3 2026  Contract value  : $10M  Estimated project value  : $75M - $100M  Type  : Consulting 
Project   : Belmont Recreation Centre Phase 2  Market timeline  : Q3 2026  Contract value  : $10M  Estimated project value  : $100M - $150M  Type  : Consulting 
Project   : Forest Lawn Civic Centre Redevelopment Phase 2  Market timeline  : Q4 2026  Contract value  : $10M - $50M  Estimated project value  : $200M - $300M  Type  : Consulting 

Transportation and open spaces

Project   Market timeline  Contract value  Estimated project value  Type 
Project   : Calgary Pathway Program – Design Bundle  Market timeline  : Q1 2026  Contract value  : >$1M  Estimated project value  : $40M  Type  : Consulting 
Project   : John Laurie Blvd & McKnight Blvd Functional Planning Study (FPS)  Market timeline  : Q1 2026  Contract value  : <$1M  Estimated project value  : $89M  Type  : Consulting 
Project   : Cushing Bridge Widening & Replacement FPS  Market timeline  : Q1 2026  Contract value  : <$1M  Estimated project value  : $70M  Type  : Consulting 
Project   : Heritage Dr & Macleod Tr at grade improvements and CPKC flyover FPS  Market timeline  : Q2 2026  Contract value  : <$1M  Estimated project value  : $95M  Type  : Consulting 
Project   : Glenmore Tr Widening from Crowchild to 14 St S.W. FPS  Market timeline  : Q2 2026  Contract value  : $1.5M  Estimated project value  : N/A  Type  : Consulting 
Project   : Brentwood Station Infrastructure Study and IC improvement FPS  Market timeline  : Q3 2026  Contract value  : <$1M  Estimated project value  : $10M  Type  : Consulting 
Project   : Pathways with Repaving – Design Bundle    Market timeline  : Q4 2026  Contract value  : >$1M  Estimated project value  : $80M  Type  : Consulting 
Project   : MacDonald Bridge Replacement/ Relocation FPS  Market timeline  : Q4 2026  Contract value  : <$1M  Estimated project value  : $35M  Type  : Consulting 
Project   : 53 St S.W. and 22X S.W. Interchange FPS    Market timeline  : Q4 2026  Contract value  : <$1M  Estimated project value  : $115M  Type  : Consulting 

Utilities Delivery

Water Utility Capital Budget and Waste and Recycling Capital Budget for 2026 is $1.14B

View the breakdown of the 2026 budget by capital program or project.

Linear infrastructure delivery

Project   Market timeline  Type  
Project   : North Calgary Water Services Valve and Pipe Supply Contracts (multiple)  Market timeline  : Q1 to Q3 2026  Type   : Construction  
Project   : North Calgary Water Services TR2, TR3 (Trenchless)   Market timeline  : Q1 2026  Type   : Construction  
Project   : McKenzie Sanitary Siphon Capacity Upgrade   Market timeline  : Q1 2026  Type   : Construction 
Project   : 9 Ave S.W. Watermain Replacement  Market timeline  : Q1 2026  Type   : Construction 
Project   : NWIC Capitol Hill Dry Pond Community Drain Improvement   Market timeline  : Q1 2026  Type   : Construction 
Project   : Penbrooke Sanitary Trunk Upgrades    Market timeline  : Q2 2026  Type   : Construction 
Project   : Prairie Gateway Feeder Main  Market timeline  : Q2 2026  Type   : Consulting  
Project   : Ogden Sanitary Siphon Upgrades   Market timeline  : Q3 2026   Type   : Construction 
Project   : Pineridge Community Drain Improvement Project   Market timeline  : Q3 2026  Type   : Construction 
Project   : Frazil Ice Boom – Bearspaw Raw 2   Market timeline  : Q3 2026   Type   : Construction 
Project   : Duck Pond Restoration  Market timeline  : Q3 2026  Type   : Construction 
Project   : Macleod Sanitary Trunk Upgrade   Market timeline  : Q4 2026  Type   : Construction 
Project   : North Calgary Water Services Linear Contract   Market timeline  : Q4 2026  Type   : Construction 
Project   : Country Hills Blvd Crosstie Feeder Main   Market timeline  : Q4 2026  Type   : Construction 

Process infrastructure delivery

Project   Market timeline  Type 
Project   : Biogas Offtake   Market timeline  : Q1 2026   Type  : Consulting  
Project   : Glenmore Water Treatment Plant Raw Water Pump Station Capacity Upgrade   Market timeline  : Q1 2026  Type  : Construction 
Project   : Blackfoot Landfill Gas Upgrade   Market timeline  : Q1 2026  Type  : Construction 
Project   : Spyhill Cell 8  Market timeline  : Q1 2026  Type  : Construction 
Project   : Design Consultant for Electrical Instrumentation, and Control (EIC)  Market timeline  : Q2 2026  Type  : Consulting  
Project   : East Calgary West Boundary Drainage   Market timeline  : Q2 2026  Type  : Construction 
Project   : East Calgary, Shepard, Spyhill Landfill Horizontal Landfill Gas   Market timeline  : Q2 2026  Type  : Construction 

Public Spaces Delivery

Design and consulting

Project Market timeline Estimated contract value Type
Project : Max Purple Extension to 84 St N.E. Detail Design​ Market timeline : Q1 2026​ Estimated contract value : $1M-$5M ​ Type : Consulting​
Project : Airport Rail Connection East Leg Detail Design​ Market timeline : Q1 2026​ Estimated contract value : $10M-$50M ​ Type : Consulting​
Project : Bridge Rehab Consulting Services RFSO​ Market timeline : Q1 2026​ Estimated contract value : Various Type : Consulting​
Project : Whitehorn Transit Oriented Development Consultant RFP​ Market timeline : Q1 2026​ Estimated contract value : <$1M ​ Type : Consulting​
Project : Barlow Max Bell Pathway Improvements​ Market timeline : Q1 2026​ Estimated contract value : <$100K ​ Type : Consulting​
Project : Bowwood Park Improvements​ Market timeline : Q1 2026​   Estimated contract value : <$300K Type : Consulting
Project : Bowness Park Lagoon Water Loss Remediation​ Market timeline : Q1 2026​ Estimated contract value : <$1M ​ Type : Consulting​
Project : Forest Lawn Civic Centre​ Market timeline : Q1 2026​ Estimated contract value : $1M-$5M ​ Type : Consulting​
Project : New Brighton Athletic Park Field Upgrades​ Market timeline : Q2 2026​ Estimated contract value : <$1M ​ Type : Consulting​
Project : Rocky Ridge Fieldhouse​ Market timeline : Q2 2026​ Estimated contract value : $1M-$5M ​ Type : Consulting​
Project : Douglasdale Habitat Restoration​ Market timeline : Q2 2026​ Estimated contract value : <$1M ​ Type : Consulting​
Project : New Main Streets Master Plan and Design​ Market timeline : Q2 2026​ Estimated contract value : $1M-$5M ​ Type : Consulting​
Project : Hawkcliff Wetland Restoration​ Market timeline : Q4 2026​ Estimated contract value : <$300K ​ Type : Consulting​
Project : Griffith Woods Riparian Restoration​ Market timeline : Q4 2026​ Estimated contract value : <$200K ​ Type : Consulting​

Mobility and transit

Project Market timeline Estimated contract value Type
Project : Pavement Rehabilitation – Various Locations​ Market timeline : Q1 2026​ Estimated contract value : $43M ​ Type : Construction​
Project : 14 Ave S.W. over 14 St S.W. Bridge Rehabilitation​ Market timeline : Q1 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : 26 Ave S.W. Mobility Improvements​ Market timeline : Q1 2026​ Estimated contract value : $10M-$50M ​ Type : Construction​
Project : Stoney Trail/Memorial Dr Flyover​ Market timeline : Q1 2026​ Estimated contract value : >$50M ​ Type : Construction​
Project : 50 Ave S.W. Mobility Improvements​ Market timeline : Q1 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : 14 Ave N.W. Reconstruction​ Market timeline : Q2 2026​   Estimated contract value : $5M-$10M ​ Type : Construction
Project : Sign Structure Lifecycle Program​ Market timeline : Q2 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Timber Stair Program​ Market timeline : Q2 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Retaining Wall Program​ Market timeline : Q2 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Bridgeland Riverside Multimodal Pedestrian Bridge – Stage 1​ Market timeline : Q2 2026​ Estimated contract value : $10M-$50M ​ Type : Construction​
Project : Dover – 34 Ave S.E. Improvements​ Market timeline : Q2 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Franklin Transit-Oriented Development (Transit Loop)​ Market timeline : Q3 2026​ Estimated contract value : $5M-$10M ​ Type : Construction
Project : Max Green Phase 3 Construction​ Market timeline : Q3 2026​ Estimated contract value : $10M-$50M ​ Type : Construction​
Project : Elbow Dr over Elbow River (Elboya) Bridge Rehabilitation​ Market timeline : Q4 2026​ Estimated contract value : $5M-$10M ​ Type : Construction​
Project : 9 Ave over 8 St S.W. Bridge Rehabilitation​ Market timeline : Q4 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Local Improvement Lane Paving RFP​ Market timeline : Q4 2026​ Estimated contract value : $1M-$5M/year (up to 5 years)​ Type : Construction

Parks and natural areas

Project Market timeline Estimated contract value Type
Project : Parks & Playground Amenities Program​ Market timeline : Q1 2026​ Estimated contract value : $1M-$5M ​ Type : Contracting​
Project : Richmond Green Park​ Market timeline : Q1 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Edworthy and Lawrey Gardens Riparian Restoration​ Market timeline : Q1 2026​ Estimated contract value : $1M Type : Construction​
Project : Sue Higgins Riparian Restoration​ Market timeline : Q1 2026​ Estimated contract value : $1M Type : Construction​
Project : Chinese Market Gardens​ Market timeline : Q1 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Red Stone Shade Structures​ Market timeline : Q1 2026​ Estimated contract value : $1M​ Type : Construction
Project : Killarney Park Improvements​ Market timeline : Q1 2026​ Estimated contract value : >$1M​ Type : Consulting/​ Construction​
Project : Carburn Park Riparian Restoration​ Market timeline : Q2 2026​ Estimated contract value : >$1M ​ Type : Consulting/​ Construction​
Project : Harvie Passage Parking Lot​ Market timeline : Q2 2026​ Estimated contract value : >$1M ​ Type : Construction​
Project : Kabaddi Park​ Market timeline : Q2 2026​ Estimated contract value : >$1M ​ Type : Construction​
Project : West Confederation Wetland and Boardwalk Construction​ Market timeline : Q2 2026​ Estimated contract value : >$1M ​ Type : Construction​
Project : Seton Regional Park ​ Market timeline : Q4 2026​ Estimated contract value : $10M-$50M ​ Type : Construction
Project : Big Marlborough Park​ Market timeline : Q4 2026​ Estimated contract value : $5M-$10M ​ Type : Construction​
Project : Indian Residential School Memorial Site​ Market timeline : Q1 2027​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Douglasdale Habitat Restoration​ Market timeline : Q1 2027​ Estimated contract value : >$1M ​ Type : Construction

Recreation and facilities

Project Market timeline Estimated contract value Type
Project : Walden Fire Station & Library​ Market timeline : Q1 2026​ Estimated contract value : $10M-$50M ​ Type : Construction​
Project : Symons Valley Centre – Phase 2 (Library, Community Commons, Multimodal Street, Parking)​ Market timeline : Q1 2026​ Estimated contract value : $10M-$50M ​ Type : Construction​
Project : Hotchkiss Temporary Fire Station​ Market timeline : Q1 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Fonda Park – Sport Field Improvements​ Market timeline : Q1 2026​ Estimated contract value : >$1M​ Type : Construction​
Project : Northeast Athletic Complex​ Market timeline : Q1 2026​ Estimated contract value : <$50M ​ Type : Construction (RFPQ)​
Project : Rockland Park Temporary Fire Station​ Market timeline : Q1/Q2 2026​ Estimated contract value : $1M-$5M ​ Type : Construction
Project : Haddon Rd Depot Redevelopment​ Market timeline : Q1/Q2 2026​ Estimated contract value : $1M-$5M ​ Type : Construction​
Project : Umoja Soccer Field​ Market timeline : Q3 2026​ Estimated contract value : >$1M ​ Type : Construction

Green Line LRT - SE project

Green Line LRT - SE project

Project   Market timeline  Type  
Project   : Ramsay/Inglewood to Event Centre/Grand Central Station​  Market timeline  : TBD​  Type   : Construction​ 
Project   : Maintenance & Storage Facility (MSF) – Site Grading, Building Foundations and Utilities​  Market timeline  : Q1 2026​  Type   : Construction​ 
Project   : MSF – Structural Steel (Supply and Install)​  Market timeline  : Q1 2026​  Type   : Construction​ 
Project   : MSF – Construction​  Market timeline  : Q2 2026​  Type   : Construction​ 
Project   : MSF – Equipment​  Material Lifts   Wheel Turning Machines   Paint Booths   Vehicle Wash  Market timeline  : Q1/Q2 2026​  Type   : Equipment 
Project   : Communications & Track Power System​  Market timeline  : Q3 2026​  Type   : Construction​ 
Project   : Communications & Track Power System (Long Lead Equipment Supply)​  Market timeline  : Q1 2026​  Type   : Equipment​ 
Project   : Signaling and Train Control System​  Market timeline  : Q3 2026​  Type   : Equipment​ 
Project   : Track​  Market timeline  : Q2 2026​  Type   : Construction 

Facilities

Calgary Fire Department

Project   Market timeline  Budget  Type 
Project   : Fire Station Diesel Exhaust System​  Market timeline  : Q1 2026​  Budget  : $1M-$5M​  Type  : Construction​ 
Project   : Various stations M&E improvements​  Market timeline  : Q1-Q2 2026​  Budget  : $5M-$10M ​  Type  : Construction​ 
Project   : Fire Station 1​  Market timeline  : Q3 2026​  Budget  : $1M-$5M ​  Type  : Construction​ 
Project   : Fire Station 15 – Parking Lot & Stairs/Ramp​  Market timeline  : Q3 2026​  Budget  : <$1M ​  Type  : Construction​ 
Project   : Fire Training Academy – Phase 2​  Market timeline  : Q3 2026​  Budget  : $5M-$10M ​  Type  : Construction 

Interior

Project   Market timeline  Budget  Type 
Project   : Multiple Fire Stations – Privacy & Accessibility Upgrades​  Market timeline  : 2026 (Multiple)​  Budget  : $5M-$10M ​  Type  : Construction​ 
Project   : Fire Training Academy and MATC Accessibility​  Market timeline  : Q3 2026​  Budget  : $1M-$5M ​  Type  : Construction​  ​ 
Project   : Manchester E 1st and 2nd Floor Modernization​  Market timeline  : Q3 2026​  Budget  : $5M-$10M ​  Type  : Construction​ 
Project   : Municipal Building 6th Floor Renovation​  Market timeline  : Q2 2026​  Budget  : $10M-$50M ​  Type  : Construction 

Recreation, parks and open spaces, and mobility

Project   Market timeline  Budget  Type 
Project   : RFSO Aquatic Upgrades and Repairs​  Market timeline  : Q1 2026​  Budget  : $5M-$10M ​  Type  : Construction​ 
Project   : Queens Park Operational Building​  Market timeline  : Q2 2026​  Budget  : $1M-$5M ​  Type  : Construction​ 
Project   : Harmony Park Cupola Restoration​  Market timeline  : Q2 2026​  Budget  : <$1M ​  Type  : Construction 

Office buildings and operations workplace

Project   Market timeline  Budget  Type 
Project   : Manchester Building Q – Multiple Projects​  Market timeline  : Q1 2026​  Budget  : $1M-$5M ​  Type  : Construction​ 
Project   : Municipal Complex Electrical Riser Upgrades​  Market timeline  : Q4 2026​  Budget  : >$50M​  Type  : Construction​ 
Project   : Construction Management RFP​  Market timeline  : Q2 2026​  Budget  : >$50M ​  Type  : Construction 

Looking for more information on working with The City on infrastructure projects? Visit Calgary.ca/IndustryRelations.

City of Calgary presentations

Public partner presentations

To view the external public partner presentations please visit the Alberta Roadbuilders & Heavy Construction Association webpage.